PM-KUSUM Component A supports decentralized, grid-connected renewable power plants developed on farmers’ land. The MNRE comprehensive guidelines of 17 January 2024 describe 500 kW to 2 MW plants, a 25-year power purchase agreement (PPA) with the DISCOM, and a preference for sites within 5 km of a notified substation. The distance is a siting preference to limit line cost and losses, not a universal statutory pass/fail rule. A state invitation and its notified substations determine which parcel can actually apply.

A farmer can develop the plant, join a group, or work through a developer. A land lease can let the farmer receive rent while the renewable power generator (RPG) builds and operates the project. The tariff, lease rent, application steps, grid works and financing must be checked for the particular state and invitation. This page follows the 2024 MNRE framework; always read later orders, the current DISCOM notice and the signed PPA before committing land or money.

Quick answer. Start with the DISCOM’s notified substation capacity and the applicable Component A invitation. Check land rights, line route, the selection method and tariff ceiling. Then prepare a site-specific layout and energy model. The 2024 national guideline does not make 19% CUF a universal Component A approval threshold or set a fixed acres-per-MW rule.

For the documents that move a selected project from concept to financing and construction, see the Component A technical-documents guide. It separates the connection, engineering, PPA and lender evidence. The Component C guide covers feeder and pump solarization, which follows a different route.

Who can participate?

MNRE’s Component A section allows an individual farmer to develop a renewable power plant directly or with a group of farmers, cooperative, panchayat, farmer producer organization or water user association. A developer can also be involved. A farmer may offer land to a DISCOM, which can act as the RPG under the guideline. The landowner’s role, plant owner, applicant and tariff recipient should be written down rather than inferred from the word “farmer.”

The model land-lease agreement is an annexure to the guidelines. Its terms may be finalized by mutual consent of the parties. The guideline does not publish a standard rent per acre or guarantee that a developer will lease a parcel. A proposed lease should identify the site, access and line rights, term, rent basis, permitted works, restoration obligations and what happens if the PPA or connectivity does not proceed. The landowner and RPG should take their own legal advice before signing.

Eligibility on paper is only the first filter. The land must connect to a notified substation with available capacity, and the developer must secure the rights and clearances the state and utility require. MNRE asks DISCOMs to assess injection capacity at rural 33/11 kV, 66/11 kV or 110/11 kV substations and publish the available capacity. A nearby transformer visible on a map is not the same as an offered connection point. Ask for the current DISCOM notice and written grid conditions.

QuestionEvidence to obtainWhy it matters
Is the applicant eligible?Current state invitation and legal entity documentsState forms and applicant categories can differ
Is the parcel usable?Title, lease proposal, survey and land-use permissionsOwnership alone does not grant every land or access right
Is the substation offered?DISCOM’s current substation-wise capacity noticeCapacity and connection point control selection
Who builds the line and bay?Connection terms and responsibility matrixChanges cost, schedule and route permissions
Is the tariff known?State regulator order and invitationThe pre-fixed rate is the ceiling if bidding is required

How much land and how close to the substation?

The national Component A text specifies plant capacity, not a fixed acreage. Land demand changes with module size, tilt, row spacing, terrain, foundations, drainage, access and the portions of the parcel that cannot be used. A land estimate made from MW alone is a feasibility placeholder. Commission a measured boundary and preliminary layout before promising that 500 kW or 2 MW will fit.

MNRE says plants should preferably sit within a five-kilometre radius of substations to avoid high sub-transmission costs and losses. The radius is not the route length. A line may detour around property, roads, railway corridors or existing utilities. The project should compare the actual feasible route and cost against the land price and expected delivered energy. The relevant invitation can impose a stricter local condition; quote that invitation if it does.

The selected RPG is responsible under the 2024 guideline for the dedicated line to the substation and the bay and switchgear where the plant connects and is metered. It may pay the DISCOM to construct the line, and multiple awarded projects at one substation may coordinate a common line with DISCOM approval. A site assessment should therefore show the plant boundary, proposed connection point, line corridor, ownership and meter boundary. The nearby-substation claim is incomplete without those details.

Application, selection and fees

The guideline permits a DISCOM to invite expressions of interest through an online portal. Applicants submit the prescribed format to the DISCOM or state implementing agency. The non-refundable processing fee may be set by the invitation but cannot exceed ₹5,000 per MW or part thereof under the 2024 national guideline. It is incorrect to tell every applicant that the charge is exactly ₹5,000 per MW. Obtain the current fee schedule and payment instructions from the actual invitation.

If the eligible capacity requested at a substation is no more than the notified available capacity, the guideline provides for letters of award at the pre-fixed levelized tariff on a first-come, first-served basis. If requests exceed available capacity, the DISCOM invites tariff bids from eligible applicants. The pre-fixed levelized tariff becomes the bid ceiling, and selection follows the lower tariffs offered through the stated closed-bid or reverse-auction process. The project team should record whether it is in the direct-award or bidding route before pricing the bid.

Under the MNRE guideline, the ₹1 lakh/MW earnest money deposit (EMD) applies in case of bidding. It is a bank guarantee, converted to a performance bank guarantee for successful bidders who sign the PPA on time. An unsuccessful bidder’s EMD is to be released within 15 days of the award to selected RPGs. A selected RPG that fails to execute the PPA within the stipulated time risks EMD encashment. Exact state tender conditions and bank-guarantee format still need checking; do not transfer an EMD clause from one invitation to another.

StageNational guideline positionProject check
Expression of interestDISCOM/SIA prescribed application; fee capped at ₹5,000/MW or partCurrent portal, fee and documents
Capacity selectionPre-fixed tariff if eligible applications fit notified capacityWritten capacity notice and award method
OversubscriptionBidding; pre-fixed tariff is ceilingBid format, dates and evaluation clauses
EMD₹1 lakh/MW in case of biddingCurrent bank-guarantee form and release terms
PPA signingWithin two months of LoA in the 2024 guidelineActual LoA and model PPA revision

For a selected project, create a controlled document list early. The technical-documents guide covers the engineering and lender evidence, while this article remains focused on the scheme route and initial siting decision.

PPA, tariff and incentive: keep the recipients separate

MNRE’s model PPA runs for 25 years from the commercial operation date. The RPG and DISCOM are the parties; the DISCOM is obliged under the guideline to buy power within the contracted capacity. The PPA is to be signed within two months of the LoA. After 25 years, the RPG may continue operation if land and other conditions allow, but an extension of the PPA requires mutual agreement. The guideline also calls for an escrow arrangement as payment security. None of these provisions means a particular plant has secured a tariff, uninterrupted dispatch or guaranteed profit. Read the actual PPA’s scheduling, metering, curtailment and payment clauses.

MNRE’s PBI incentive to the DISCOM is separate from the RPG’s sale of electricity. The 2024 guideline sets it at ₹0.40 per unit purchased or ₹6.6 lakh per MW of installed capacity per year, whichever is lower, for five years from commercial operation. MNRE pays the DISCOM after the required reporting. The DISCOM may pass the incentive on to the plant owner if it chooses. Do not include that PBI as automatic RPG revenue in a financial model. The current state tariff and signed PPA determine the RPG’s electricity revenue.

Component A does not provide central financial assistance (CFA) to the RPG in the form described for some pump and feeder components. That distinction matters when comparing it with Components B and C. It does not mean financing is easy: project capital cost, lease, grid connection, debt terms, taxes and actual generation all affect viability. A bank or IREDA appraisal is project-specific. Avoid using a generic 70:30 debt ratio or an old interest-rate range as a financing promise.

Build a defensible energy and design basis

There is no universal Component A rule that every plant must achieve 19% capacity utilisation factor (CUF). A 19% minimum CUF appears elsewhere in the MNRE comprehensive document for a Component C feeder-level sizing/CFA calculation; it should not be copied onto Component A as a financing or approval condition. A Component A tender or PPA may set generation obligations of its own. Quote the exact clause and measurement point if it does.

For a teaching example, a hypothetical 1 MW AC plant delivering 1,664,400 kWh in a non-leap year has a CUF of 19% at that named point: 1,664,400 ÷ (1,000 × 8,760) = 0.19. This is arithmetic, not a forecast. If the meter is beyond a transformer or evacuation line, delivered energy differs from inverter output. Do not compare a DC nameplate denominator with an AC metered-energy target without explaining the convention.

The first useful engineering inputs are a topographic and boundary survey, site shading and obstacle information, current weather-data source, proposed module and inverter envelope, land exclusions, preliminary row layout, soil and drainage information, and written grid connection conditions. A PVsyst or other yield study should show assumptions, losses, result location and sensitivity to equipment and layout changes. It cannot “confirm” a 25-year result from a preliminary satellite image.

A layout should leave access and maintenance routes, check inter-row shade against the design objective, and coordinate structure, cable paths and drainage. The optimum tilt is a model result for a particular site and cost objective, not always “latitude minus 5 degrees.” A string schedule must use selected module and inverter data, with cold open-circuit voltage, hot operating voltage, current and MPPT checks. Electrical, structural and civil sheets should carry the same equipment and capacity revisions.

The SLD should show the plant and grid boundary, transformer, switching, metering and protection concept. The line and bay package depends on the DISCOM’s approved connection condition. An earthing drawing and design calculation are separate deliverables where required. The responsible engineer should apply the current CEA rules, state requirements and relevant standards; a web article cannot supply universal relay settings, cable voltage-drop limits or inspection acceptance.

Timelines, maintenance and the next decision

The 2024 MNRE guideline sets commissioning within 15 months from LoA. Its penalty section provides proportionate daily PBG encashment for delay up to six months, then reduction of PPA capacity to what was commissioned at the end of that period. It also allows the DISCOM to extend time without financial implication when satisfied by documentary evidence of causes beyond the RPG’s control. Later scheme orders or a specific LoA may change the practical date, so track the actual project documents rather than a generic “12–18 month” estimate.

After commissioning, the RPG needs an O&M plan for safe operation and generation reporting. Cleaning frequency depends on measured soiling, water access, season and the economics of cleaning; twice a month is not a national rule. Keep commissioning tests, as-built drawings, meter records, faults, inverter events and maintenance logs. Compare actual output with a weather-adjusted expected profile before attributing a shortfall to one cause. Neither a fixed annual CUF target nor a ₹/MW monitoring cost can be promised without a project model and vendor quote.

For a project-specific engineering scope, send the current DISCOM invitation, substation notice or connection letter, site survey, land constraints, target capacity and PPA draft through the contact route. Heaven Designs lists site feasibility, layouts, SLDs, PVsyst reports, structural and electrical drawings among its engineering deliverables. The response can define the exact scope, price and delivery date after reviewing the inputs. The state authority, DISCOM and lender make their own approval and financing decisions.

Common questions

Is five kilometres an absolute land-eligibility limit?

The 2024 MNRE guideline says preferably within a five-kilometre radius, to limit line cost and losses. A state invitation may make distance a stricter condition. Check the offered substation and actual route before relying on a parcel.

Does every Component A application cost ₹5,000 per MW?

No. The national guideline caps the non-refundable processing fee at ₹5,000 per MW or part thereof. The DISCOM invitation gives the fee actually payable. The ₹1 lakh/MW EMD in the guideline applies in case of bidding.

Does MNRE require 19% CUF for Component A?

The Component A section does not set that universal minimum. Use the generation terms of the current tender and PPA, and a site-specific yield model. The 19% arithmetic example above is for explaining CUF only.

Can a farmer lease land to a developer?

Yes, the guideline allows development through a developer and includes a model lease. Rent and terms are negotiated; it does not publish a standard ₹/acre rate. Confirm land title, line access and lease duration with legal advisers.

Who pays for the line and substation bay?

The selected RPG is responsible for the dedicated line, bay and related switchgear under the 2024 guideline, with an option to pay the DISCOM to construct the line. The actual agreement and project allocation should be checked before pricing.