When a solar plant connects to the Indian grid, the DISCOM protection engineer will not sign the synchronisation permit until the developer submits a relay coordination study that proves the plant protection relays operate faster than the upstream grid relays during every credible fault condition. This is not a checkbox exercise.

A poorly coordinated protection scheme creates two equally bad failure modes: the plant trips for every minor grid disturbance (causing unnecessary revenue loss), or the plant relays do not trip fast enough to isolate a fault before the DISCOM upstream breaker operates (causing a sustained fault that damages transformer windings or HV cables worth crores to replace).

Quick answer. A solar relay coordination study for India follows the 4-Step Relay Coordination Methodology: fault current calculation at the point of common coupling (PCC), protection relay selection (IDMT overcurrent, directional, differential, distance), time-current grading using IEC 60255-151 IDMT curves, and coordination curve verification against the upstream DISCOM relay. The utility’s connection conditions and the protection study fix the relay functions and settings, within the CEA technical standards for connectivity. The output is a relay settings report that the DISCOM protection engineer countersigns before commissioning, derived from software tools such as ETAP, ERACS, or PowerWorld.

This guide is written for Suresh and his engineering team preparing a relay coordination submission for a 25 MW solar project connecting at 33 kV in Rajasthan. The methodology applies equally to 66 kV and 132 kV interconnections, with additional relay functions required at the higher voltage classes, where substation layout and earthing design also become more demanding.

TL;DR

  • Relay coordination follows a 4-step methodology: fault current calculation at the PCC, protection relay selection, time-current grading, and coordination curve verification.
  • Relay settings for under/over-voltage, under/over-frequency and anti-islanding protection are fixed by the utility's connection conditions and the protection study. The CEA connectivity standards do not give one settings table for every plant.
  • Adjacent relays must maintain a coordination margin of at least 0.3-0.4 seconds at every fault current level, using IEC 60255-151 IDMT curves.
  • ETAP is the dominant study software in India, accepted by SECI, NTPC, and most STUs; ERACS and PowerWorld see limited, state-dependent acceptance.
  • DISCOM or STU review time is set by the utility's own procedure and varies by state. Ask for the review period and the submission format in writing, and expect a resubmission to be reviewed again.
  • Heaven Designs prepares complete relay settings reports, with turnaround agreed at scoping.

What Relay Coordination Is and Why DISCOM Requires It

Relay coordination is the process of setting the operating characteristics of multiple protection relays in series so that the relay nearest to the fault operates first, isolating the minimum section of the network. All relays further from the fault provide backup, operating after a deliberate time delay if the primary relay fails.

Definition. A protection relay is a device that monitors electrical quantities (current, voltage, frequency, impedance) and issues a trip command to a circuit breaker when a measured quantity exceeds a pre-set threshold. Relay coordination ensures that, in a network with multiple relays in series, only the relay closest to the fault operates, preserving supply to the rest of the network and limiting equipment damage to the minimum necessary section.

The DISCOM requires a relay coordination study before synchronisation for two reasons. First, grid stability: an uncoordinated solar plant protection system can cause the plant to disconnect from the grid at the wrong time, either too early (nuisance tripping during minor voltage dips) or too late (allowing a fault to persist until the DISCOM upstream breaker operates, causing a wider outage).

Second, equipment protection: the thermal and electromagnetic limits of transformers, cables, and switchgear are well-defined, and a relay coordination study calculates whether the protection system will isolate a fault before fault current causes irreversible thermal damage.

In practice, the utility expects the developer to complete and submit the relay coordination study before it issues a grid connectivity approval (GCA). The exact requirement is in the utility’s own connection procedure, so confirm it with the DISCOM or STU. Projects that proceed to energisation without a GCA face penalties under the Electricity Act 2003.

The 4-Step Relay Coordination Methodology

Heaven Designs follows a structured four-step process for every relay coordination study, regardless of project capacity or voltage level. This process ensures that the output relay settings report satisfies the DISCOM protection engineer review without requiring a second submission.

1

Fault Current Calculation at the PCC

Calculate the maximum and minimum three-phase and single-phase-to-earth fault currents at the point of common coupling and at every other protection relay location in the plant. Maximum fault current (using minimum grid impedance) sets pickup thresholds; minimum fault current (using maximum grid impedance) verifies that relays operate for the smallest credible fault.

2

Protection Relay Selection

Select the relay types, IED models, and CT/VT ratios for each protection function. At 33 kV, the standard set includes IDMT overcurrent (51), earth fault (51N), under/over-voltage (27/59), and under/over-frequency (81U/81O). At 132 kV, add distance protection (21), transformer differential (87T), and directional earth fault (67N). Document the manufacturer, model number, firmware version, and available characteristic curves for each relay.

3

Time-Current Grading

Plot the time-current characteristics of every relay in the protection chain on the same logarithmic time-current graph. Adjust the time-multiplier setting (TMS) of each relay so that the plant relay operates before the upstream DISCOM relay by a minimum coordination margin of 0.3-0.4 seconds. The IDMT curve shape, Normal Inverse, Very Inverse, or Extremely Inverse, must be selected to achieve coordination across the full fault current range.

4

Coordination Curve Verification

Verify the final relay settings against three tests: (a) the relay operates for the minimum fault current at the far end of the protected zone; (b) the coordination margin is maintained at every fault current from minimum to maximum; (c) the operating time of each relay does not exceed the thermal withstand time of the protected equipment. Document the verification results in tabular form for the DISCOM submission.

Fault Current Calculation at the Point of Common Coupling

The fault current calculation is the foundation of the entire relay coordination study. An error here propagates through every subsequent step, producing relay settings that are either too sensitive (causing nuisance trips) or too insensitive (missing real faults).

16-40 kA

Typical 33-132 kV bus fault level in India

CEA annual report on grid parameters, 2024

0.3 s

Minimum coordination margin (grading time)

IEEE C37.91, standard grading practice

1.1-1.5x

Solar inverter fault current output

IRENA grid integration guidelines, 2023

The fault current at the PCC has two sources: the upstream grid (the dominant source carrying 90-99% of fault current for most plant configurations) and the solar plant itself (limited by inverter current limiting to 1.1-1.5 times rated output current).

For relay coordination purposes, the contribution from the solar plant is typically small enough to treat as negligible for radial feeder configurations, but it must be calculated and verified, especially for projects at the end of a weak 33 kV feeder where the grid fault current is low.

The fault current calculation follows the symmetrical components method as described in IEEE Standard C37.113 (Guide for Protective Relay Applications to Transmission Lines). The inputs required from the DISCOM are the positive-sequence impedance of the grid at the PCC, the zero-sequence impedance for earth fault calculations, and the maximum and minimum fault MVA at the PCC from the DISCOM power system model.

Request these values in writing from the DISCOM protection engineer as part of the grid connectivity application.

Relay Types Used in Solar Protection

The relay types used in a solar plant protection scheme are determined by the interconnection voltage, the plant configuration, and the DISCOM specific requirements. A site that must not export at all adds a reverse power relay and an export controller, which our zero export solar design guide covers.

Relay FunctionIEEE NumberApplicationVoltage Class
IDMT Overcurrent51Line feeder, transformer HV33 kV and above
Earth Fault51NLine feeder, transformer neutral33 kV and above
Directional Overcurrent67Ring bus, parallel feeders66 kV and above
Directional Earth Fault67NRing bus, parallel feeders66 kV and above
Distance21Transmission line132 kV and above
Transformer Differential87TMain power transformer33 kV and above (recommended)
Under/Over Voltage27/59PCC busAll voltage classes
Under/Over Frequency81U/81OPCC busAll voltage classes
Anti-islanding27/59/81 combinationPCC busAll voltage classes
Reverse Power32HV feederNet metering projects

IDMT Overcurrent (51) setting methodology for solar plants:

The pickup current (Is) for the 51 relay must satisfy two conditions: it must be above the maximum continuous load current (including the maximum export current from the solar plant), and it must be below the minimum fault current at the far end of the protected zone.

For a 25 MW plant at 33 kV with a rated output current of 437 A at the PCC:

  • Maximum load current = 437 A
  • Pickup current setting minimum = 437 A x 1.2 = 524 A
  • CT ratio = 600/1 A (selected above full load)
  • Pickup setting in CT secondary amps = 524 / 600 = 0.87 A (set to 0.9 A)

The time-multiplier setting (TMS) is calculated by selecting the IDMT curve (Very Inverse is typical for solar feeders) and adjusting the TMS until the operating time at minimum fault current provides the required 0.3-second grading margin with the DISCOM upstream relay.

Field tip. Always verify the relay pickup setting against the minimum fault current at the furthest point in the protected zone, not just the maximum fault current at the relay location. A relay that is set too insensitively may fail to operate for a high-impedance fault, such as a single conductor touching dry soil, even though it would operate correctly for a bolted three-phase fault.

Typical Relay Settings for a 33 kV Solar Plant (Illustrative)

The table below shows typical, illustrative settings for a 33 kV solar plant. They are not taken from the CEA regulations. The utility’s connection conditions and the protection study fix the real settings for each project, so treat these as a starting point to confirm with the DISCOM or STU. One check applies at the CEA level: the CEA (Technical Standards for Connectivity to the Grid) Amendment Regulations notified on 15 October 2013 (Internet Archive capture of the CEA gazette PDF) require generating units to be capable of operating in the 47.5 Hz to 52 Hz range and delivering rated output between 49.5 Hz and 50.5 Hz. Frequency trip settings must not defeat that capability.

Protection FunctionTypical Illustrative Setting (33 kV)Operating Time
Under-voltage (27)Trip below 0.85 pu for more than 0.2 sUnder 0.2 s
Over-voltage (59)Trip above 1.15 pu for more than 0.2 sUnder 0.2 s
Under-frequency (81U)Trip below 47.5 Hz for more than 0.2 sUnder 0.2 s
Over-frequency (81O)Trip above 51.5 Hz for more than 0.2 sUnder 0.2 s
Anti-islandingDetect islanding within 0.2 s; trip within 0.5 sUnder 0.5 s
IDMT Overcurrent (51)Set above 120% of full load currentPer IDMT curve and TMS

For LVRT (low-voltage ride-through) compliance, the plant must remain connected during the voltage dips that the applicable grid code or connection conditions require it to ride through. Take the ride-through curve from those documents, then set the under-voltage (27) relay time delay so that it does not trip the plant inside that curve. The relay settings report must explicitly demonstrate this LVRT/27 relay interaction.

The developer submits the relay settings report to the DISCOM or STU for review and approval before commissioning. The review period and the format are set by the utility’s own procedure, so ask for both in writing at the start.

Time-Current Grading, IDMT Curves and Coordination Margin

Time-current grading is the process of plotting the operating time of every relay in a protection chain as a function of fault current and verifying that adjacent relays are separated by the minimum coordination margin.

The standard IDMT curve equations defined in IEC 60255-151 are:

Normal Inverse (NI): t = TMS x (0.14 / ((I/Is)^0.02 - 1))

Very Inverse (VI): t = TMS x (13.5 / ((I/Is) - 1))

Extremely Inverse (EI): t = TMS x (80 / ((I/Is)^2 - 1))

Where t is the operating time in seconds, TMS is the time-multiplier setting, I is the fault current, and Is is the pickup current setting.

The coordination margin between adjacent relays must be at least 0.3 seconds at every fault current level. This margin accounts for the circuit breaker interruption time (typically 60-100 ms for modern vacuum circuit breakers at 33 kV), the relay timing tolerance (typically plus or minus 5% per IEC 60255-151), and a safety allowance for circuit breaker failure.

Watch out. Using Normal Inverse curves for solar projects with a high ratio of maximum to minimum fault current (greater than 10:1) often makes it impossible to achieve coordination at both ends of the fault current range simultaneously. In these cases, switch to Very Inverse or Extremely Inverse curves, which have a steeper slope that provides better discrimination at low fault currents without excessive operating time at high fault currents.

How to Submit Relay Setting Documents to the DISCOM

The relay settings submission to the DISCOM protection engineer must be a complete, self-contained technical document. A submission that requires the DISCOM engineer to make assumptions or request additional information will be returned, resetting the review clock.

The relay settings report must include:

  1. Project description page: Project name, capacity, location, voltage class, PPA reference number, developer name, and engineering consultant name.
  2. Single-line diagram extract: A simplified SLD showing only protection-relevant elements (transformers, circuit breakers, CTs, VTs, and relay designations). Refer to our full guide on solar HV interconnection drawings for the complete SLD specification.
  3. Short-circuit study results: Tables of maximum and minimum fault current (three-phase and single-phase) at every relay location, with the grid impedance data provided by the DISCOM.
  4. Relay specification table: For every relay: manufacturer, model, function number, CT/VT ratio, pickup setting, time-multiplier setting, and characteristic curve.
  5. Coordination curves: Logarithmic time-current plots showing all relays in the coordination chain simultaneously. Plots must be generated from study software (ETAP, ERACS, or equivalent), hand-drawn curves are not accepted.
  6. IDMT curve calculations: Tabulated operating times at relevant fault current levels for each relay, showing the grading margin at each level.
  7. Anti-islanding verification: Calculation demonstrating that the combined action of 27/59/81U/81O relays will detect and trip for islanded operation within 0.5 seconds.
  8. LVRT compatibility check: Confirmation that the 27 relay time delay is consistent with the plant LVRT capability and the relay will not trip during a voltage dip the inverter is required to ride through.

See also our guide on CEA connectivity regulations for solar projects for state-specific addenda that some DISCOMs require alongside the standard CEA format. For projects requiring lenders to review the protection scheme, see our article on lenders due diligence and engineering in India.

Ask which design example can be shared.

Redacted relay coordination study for a 25 MW, 33 kV solar project in Rajasthan, includes short-circuit study results, ETAP coordination curves, and DISCOM submission format.

Ask About an Example

Software Tools for Relay Coordination Studies

Three software platforms dominate the Indian market for relay coordination studies on solar projects.

ETAP (MOST COMMON IN INDIA)

  • Most widely specified by Indian DISCOMs and independent engineers
  • Full short-circuit, coordination, and arc flash modules integrated
  • Accepted by SECI, NTPC, and most STUs as the reference tool
  • Higher licence cost: ₹3-8 lakhs per year

ERACS AND POWERWORLD

  • ERACS has strong relay library for IEC 60255-151 curves
  • PowerWorld has better load flow capabilities for large networks
  • Less common in India, DISCOM acceptance varies by state
  • Lower licence cost than ETAP

The relay settings report must state the software name, version, and licence number used for the study. Some DISCOMs ask for the software model file (.etap or equivalent) alongside the PDF report so their in-house protection engineers can verify the inputs.

Include the relay manufacturer’s test certificates in the commissioning documentation, not just the relay settings report. Check the utility’s connection conditions for the testing and certification the relays must carry.

How Heaven Designs Helps with Relay Coordination

Most Indian EPC contractors complete relay coordination studies once or twice per year at most, not frequently enough to maintain in-house expertise in ETAP or the nuances of DISCOM submission formats across different states. The result is often a study that gets returned by the DISCOM protection engineer with technical comments, which delays commissioning.

This infrequency is one of the reasons EPCs increasingly outsource specialised solar engineering work such as protection studies rather than build the capability in-house.

Heaven Designs maintains a dedicated protection engineering team that has completed relay coordination studies for projects across Rajasthan, Gujarat, Karnataka, Andhra Pradesh, Tamil Nadu, and Maharashtra.

For projects approaching the synchronisation milestone with a pending relay setting approval, contact us and we reply within 1 business day. The study starts from the DISCOM grid impedance data and the as-built SLD, with turnaround agreed at scoping.

FAQ

What is relay coordination and why is it needed for solar projects?

Relay coordination ensures that protection relays in a solar plant operate in the correct sequence during a fault, the relay nearest the fault operates first, isolating the minimum section of the network, while relays further away provide time-delayed backup.

Without coordination, the upstream DISCOM relay may operate before the plant relay, causing a wider outage and potential equipment damage. Utilities typically ask the developer to submit a relay coordination study demonstrating correct grading before they issue a grid connectivity approval.

What is an IDMT relay and which curve should I use for a 33 kV solar feeder?

An IDMT (Inverse Definite Minimum Time) relay is a protection relay whose operating time varies inversely with the fault current, the higher the fault current, the shorter the operating time. Three standard IDMT curve shapes are defined in IEC 60255-151: Normal Inverse, Very Inverse, and Extremely Inverse.

For 33 kV solar feeders with a fault current ratio (maximum to minimum) greater than 5:1, Very Inverse curves are recommended because they provide better discrimination at intermediate fault current levels without being excessively slow at minimum fault current.

How do I get the grid impedance data needed for the relay coordination study?

Request the grid impedance data from the DISCOM protection engineer as part of the grid connectivity application. The standard request includes the positive-sequence and zero-sequence Thevenin impedances at the PCC under maximum and minimum grid strength conditions, the maximum and minimum three-phase fault MVA at the PCC, and the operating time-current characteristics of the upstream DISCOM relay at the injection substation.

Most state DISCOMs in India have standard forms for this request. In Rajasthan (RVPNL), submit Form NR-1; in Gujarat (GETCO), submit Form G-7C.

How long does DISCOM relay setting approval take?

We have no published review period to quote. The time is set by each utility’s own procedure (for example RVPN in Rajasthan or GETCO in Gujarat) and depends on how complete the submission is and how many technical comments follow. Ask the utility for its review period and the departments involved in writing before you plan the synchronisation date.

Expedite the process by submitting the relay settings report simultaneously with the short-circuit study and the SLD, staggered submissions cause DISCOM engineers to hold the entire file until all documents are available.

Can string inverter solar plants use the same relay coordination methodology as central inverter plants?

The relay coordination methodology is the same, but the fault current contribution from string inverters is lower than from central inverters. String inverters current-limit to approximately 1.1-1.2 times rated output during a fault.

This low fault current contribution makes it important to calculate the minimum fault current scenario carefully, the plant relay must be able to detect a fault even when the inverters are contributing negligible current and the grid fault current at the plant 33 kV bus is at its minimum during light-load conditions.

What happens if the DISCOM rejects the relay settings report?

The DISCOM will issue a technical comments letter specifying the reasons for rejection, typically incorrect pickup settings, insufficient coordination margin at a specific fault current level, or missing documentation such as the LVRT compatibility check.

The developer must revise the relay settings report addressing every comment and resubmit the full document, not just the revised pages. The utility will review the resubmitted report again, and its own procedure sets how long that takes. Two rejections at the same project are rare if the study is performed by an experienced protection engineering team.

Does the relay coordination study need to be stamped by a licensed electrical engineer?

Who must sign the relay settings report is set by the utility’s connection procedure and the state’s electrical inspectorate rules. Check both, and expect the report to be signed by a qualified electrical engineer engaged by the developer.

India does not use a state PE stamp system equivalent to the USA, but the CEIG may require the protection scheme drawing and relay settings summary to be countersigned by the developer licensed electrical contractor. See our detailed guide on the CEIG drawing approval process in India for state-specific requirements.

Which software does Heaven Designs use for relay coordination studies?

Heaven Designs uses ETAP (version 21 and above) as the primary tool for relay coordination studies because it is the most widely accepted platform by Indian DISCOMs and SECI independent engineers.

For projects requiring PowerFactory DiGSILENT (requested by some state STUs for dynamic stability studies), Heaven Designs maintains access through its subcontract protection engineering network. All study output files and PDF reports are provided to the client, this transparency allows the DISCOM protection engineer to review the input assumptions directly if they request it.