A solar design scope of work should let both parties answer the same five questions: what will be designed, from which inputs, to what issue level, by whom, and how acceptance will be decided. The copyable template below is for an EPC or developer buying engineering services. It is deliberately a buyer-side document: it states the project boundary and expected handover before a supplier prices the work. Our solar design RFP guide addresses the wider procurement process and comparing responses. Use this page when you need the actual scope text.

The template is a starting point, not a contract or a substitute for a licensed engineer’s review. Replace every bracketed field. Remove irrelevant deliverables. Add the actual site, authority, equipment, and client specification. Do not assume that a full design package, permit submission, stamped document, source-file handover, or as-built update is included unless the signed agreement says so. The US Department of Energy’s solar procurement guidance similarly treats technical specifications as system- and site-specific. The same principle matters in India, where utility and state requirements differ by project.

Before copying: choose the project stage

A bid-stage scope may need a layout, indicative SLD, preliminary quantities, and yield assumptions. An IFC scope needs coordinated construction information based on verified site and selected equipment. An authority-submission scope needs the actual application format and review conditions. An as-built scope needs field evidence. Mixing all four into the phrase “complete solar design” leads to price disputes and missing deliverables.

StageMain decision supportedInputs that must be credibleTypical output boundary
Feasibility or bidIs the project worth pursuing and at what approximate configuration?Available site plan, rough capacity target, equipment assumptions.Indicative drawings and assumptions, not construction release.
Client or authority submissionCan the proposed design be reviewed against a named requirement?Submission checklist, approved site and electrical basis.Application package and response to defined comments.
IFCCan the EPC procure and construct the approved design?Verified survey, selected equipment, coordinated disciplines.Controlled construction drawings, schedules, and calculations.
As-builtWhat was actually installed and accepted?Redlines, measurements, equipment records, approved changes.Updated operating record and handover index.

These are scope categories, not claims about a particular jurisdiction. The actual deliverable list must be attached as a schedule.

Copyable solar design scope of work

The following text is intended to be pasted into an EPC’s procurement document and completed. Keep the numbered headings so a bidder can respond line by line. If a field is unresolved, state the decision owner and date needed rather than filling it with an invented value.

1. Project and parties

Project: [name and unique ID]. Site: [address, coordinates, state and utility territory]. Buyer: [EPC/developer legal entity]. Engineering supplier: [name or “to be selected”]. Owner/end client: [name, if authorised to disclose]. Project type: [rooftop, ground mount, floating, carport, hybrid]. Current stage: [bid, permit, IFC, as-built]. Scope effective date: [date]. Primary technical contacts: [roles and contact route].

Use the legal project ID and site location on all issued drawings. If the supplier will communicate with the end client or authority, say whether it does so directly or through the EPC. This prevents an engineer from submitting a revision that the EPC has not reviewed.

2. Design objective and system boundary

The supplier shall prepare the deliverables in Schedule A for [defined issue purpose]. The design boundary begins at [PV modules/array area] and ends at [point of interconnection or other defined boundary]. Target DC capacity is [kWp or MWp] and target AC capacity is [kW or MW]. The export limit, if applicable, is [value and source]. The design shall use the accepted inputs in Schedule B and identify unresolved assumptions in an assumptions register.

This paragraph separates DC and AC units and makes the electrical boundary visible. If battery storage, DG interaction, transformer design, evacuation line, civil work, or grid study is involved, include each explicitly. A generic “solar plant” phrase cannot resolve who owns those interfaces.

3. Inputs provided by the buyer

The buyer will supply the latest [survey/site plan], [roof or geotechnical and structural information], [electrical single-line or point-of-connection information], [module and inverter data], [client technical specification], [authority or DISCOM requirements], [existing drawings], and [field information]. Each supplied file shall have a date, revision, source, and known limitation in Schedule B. The supplier shall notify the buyer when an input is missing or inconsistent before using an assumption that could affect a construction or submission decision.

Include a table of actual attachments. If the roof cannot be accessed, state that. If a utility approval is pending, attach the application and comments. The supplier should not be asked to certify an unseen roof or guarantee a utility outcome. The buyer’s obligation to provide reliable inputs is as important as the supplier’s drawing obligation.

4. Design basis and applicable requirements

The supplier shall create a design-basis register identifying the project specification, contract requirements, authority instructions, adopted codes or standards, equipment datasheets, site conditions, and calculation assumptions used for each discipline. The buyer will confirm the jurisdiction and any required approval format. Conflicts among these inputs shall be raised for written disposition before the affected deliverable is issued.

Do not paste a code list from another country. For a US permit project, the local authority having jurisdiction and utility determine the applicable submission details. DOE confirms local US permitting rules vary. For an Indian project, name the relevant state, DISCOM, CEIG process where applicable, and client specifications. The scope should point to dated primary documents, not to a generic statement such as “all current codes.”

5. Deliverables and formats: Schedule A

The supplier shall provide only the items marked “included” in the table below. Each issue shall include a drawing/document register, revision, issue purpose, date, and transmittal. The agreed editable formats, PDF formats, sheet sizes, and model files are recorded for each item. Excluded items shall be shown explicitly.

DeliverableIncluded?Issue purposeInput dependencyAcceptance check
Array/site layout[yes/no][bid/permit/IFC/as-built]Survey, access, equipment dimensions.Coordinates, array count, setbacks and key notes agree with basis.
Single-line diagram[yes/no][purpose]Interconnection data, equipment schedule.Ratings, device IDs, topology and capacity agree with schedules.
Stringing or DC plan[yes/no][purpose]Module/inverter data, layout.String counts and inverter assignments reconcile.
Cable schedule and sizing[yes/no][purpose]Route, installation method, loads.Cable IDs, routes, calculations and SLD reconcile.
Earthing/bonding plan[yes/no][purpose]Site and equipment basis.Paths, tags and details coordinate with electrical drawings.
Mounting/structural package[yes/no][purpose]Roof/foundation data, loads.Reviewer, load basis and details are identified.
Energy-yield model[yes/no][purpose]Weather and loss assumptions, equipment.Inputs, losses and output version are traceable.
BOQ/equipment schedule[yes/no][purpose]Coordinated design.Quantities and model IDs reconcile with drawings.
Authority response matrix[yes/no][purpose]Actual comments and submission.Every comment has a disposition and revised-sheet reference.
As-built update[yes/no][purpose]Verified field redlines and changes.Record matches accepted installation evidence.

The list is intentionally broad. Remove rows that do not apply and add project-specific deliverables. Identify who supplies specialised studies and signatures. If the buyer requests “stamped drawings,” state the jurisdiction and licensed professional arrangement in the signed scope; do not treat a generic design vendor as automatically authorised to stamp every location.

6. Review, issue sequence, and acceptance

The supplier will issue [named milestone packages] in the agreed sequence. The buyer’s technical lead will provide one consolidated comment register for each package within [agreed review period]. The supplier will respond to each comment with a disposition and revised-document reference. Acceptance occurs when the buyer confirms that the agreed Schedule A deliverables have been issued at the specified purpose and the open-comment list is closed or expressly transferred to a later stage.

Do not equate “emailed” with “accepted.” A deliverable may be issued on time but contain unresolved conflicts. Conversely, a buyer may delay feedback. Define the evidence and process for both situations in the agreement. Keep authority acceptance separate from buyer acceptance; the engineer can prepare a submission but cannot guarantee the authority’s decision.

7. Changes, assumptions, and exclusions

A change in site condition, equipment model, export limit, owner requirement, authority comment, or project stage that alters the agreed design basis will be recorded in a change log. The parties will agree on revised scope, price, and delivery date before extra work proceeds, except for any separately agreed urgent instruction. Exclusions are [list]. Provisional assumptions are [list], each with a decision owner and latest confirmation date.

This is operational language, not legal advice. The signed contract should define notices, liability, payment, and dispute terms. Explicit exclusions might include site survey, structural testing, utility fees, permit submission, procurement, construction supervision, and redesign caused by post-freeze equipment changes. Include an item only if it is truly excluded; hiding a critical task under “by others” creates a gap.

8. Handover and file control

At each milestone the supplier shall issue a dated transmittal and current document register. At final acceptance the supplier shall provide the agreed PDFs, editable files, calculation outputs, model inputs, assumptions and change logs listed in Schedule A. The parties shall identify any licensed or third-party material that cannot be transferred. Superseded files shall be clearly marked.

The NREL PV O&M guide explains why a controlled record, as-built drawings, equipment data, and commissioning information matter for operations. Design handover should anticipate that later use. A folder of unlabelled PDFs may satisfy a superficial delivery count while failing the owner who must maintain the plant.

How to use the template in a real purchase

First, fill the project identity, boundary, and authority fields with verified facts. Second, mark every deliverable included or excluded. Third, attach actual source documents and their revisions. Fourth, ask the supplier to list deviations and missing inputs against each clause. Fifth, agree the acceptance and change path before work starts. If price is compared across suppliers, ensure they price the same issue stage and file formats.

A useful pre-award question is: “What would prevent you from issuing this package on the proposed date?” A capable supplier should be able to name missing surveys, equipment approvals, authority details, or review windows. The answer helps the buyer improve the scope. Treat a promise based on unstated inputs as a risk to manage, not as a guarantee of efficient delivery.

The template does not make a technical design complete by itself. It creates a shared boundary so engineering can be reviewed against a known assignment. For the vendor-selection process, use the RFP response guide. For help turning a project scope into a design assignment, send the filled identity and deliverable schedules through the Heaven Designs project contact form. We can review the inputs and reply with a proposed scope, price, and delivery date.

Sources and application note

Checked 23 November 2026: DOE FEMP solar procurement guidance, DOE US permitting guidance, and NREL PV O&M document-management guidance. Template clauses and tables are original editorial examples. Adapt them to the signed contract, actual jurisdiction, and engineering responsibility.

A final redline check before signing

Read the completed scope as if you were the incoming engineer with no access to the sales conversation. Every important noun should have an owner and a document: “site survey” should identify a revision and date; “approved equipment” should point to model data; “permit set” should name the authority and submission checklist; “final package” should have a deliverable schedule. If these anchors are absent, ask the buyer to supply them or create an explicit assumption before the engineering price is fixed.

Read the scope again as the EPC construction manager. Can the field team tell which drawing issue it will receive? Can it identify what happens if the physical site differs from the supplied survey? Is the response route for an urgent RFI clear? Will the design team update related schedules when one sheet changes? These questions often expose the difference between a drawing purchase and a coordinated construction package.

Finally, read it as the plant owner. Will the agreed handover let a future technician identify installed equipment, cable routes, and the current SLD? Does the as-built requirement name who supplies field evidence? If not, add an operating-record handover before the purchase order is placed. The cost of clarifying that obligation now is usually smaller than reconstructing it after the site team has demobilised; the exact commercial impact depends on the project.