A solar + diesel generator (DG) single-line diagram should make the site’s operating states legible. A reviewer needs to see where utility supply, PV inverter output, generator output and site loads meet; which source establishes voltage and frequency in each state; where power flow is measured; and what trips or curtails PV when a permitted operating limit is approached. A conventional grid-connected PV SLD that simply adds a DG symbol does not answer those questions.
The drawing is an engineering communication tool, not a substitute for controller settings, a protection study or commissioning tests. For an Indian EPC, the approved design must also match the actual utility or authority conditions for the site. The Central Electricity Authority maintains the 2013 distributed-generation connectivity regulations and 2019 amendment. Check the adopted requirements and the specific connection approval before deciding what the SLD must show.
Conceptual information flow only. This is not a wiring or protection design; the project drawing needs checked equipment, settings and approval conditions.
This guide is about how to represent the hybrid arrangement on the SLD. It does not size the controller, choose a generator, or set relay values. Those decisions require the equipment documentation, load profile, fault data and project study. Use the drawing checklist below to make the proposed control and protection scheme reviewable before an EPC buys hardware or issues a construction set.
Why a DG site needs a different solar SLD
On a simple grid-connected rooftop plant, the normal power path is relatively easy to trace: PV strings feed inverters, inverters feed the AC board, and the board connects to the consumer installation and utility. When the utility is unavailable, a standard grid-following inverter ordinarily cannot continue energising an isolated AC bus unless a compatible source and control architecture have been specifically designed for that mode. A DG-backed site introduces more than one possible source state.
The SLD should identify at least four possible states for discussion: utility present with PV operating, utility absent with DG running, transfer between utility and DG, and a fault or protection trip. Some sites also have battery storage, multiple generators, or an intentional islanding system; those need additional states. The drawing should say which of these states the project is designed to support. It must not imply that solar will remain available during every power cut merely because a DG set exists.
The critical distinction is between the electrical connection and the control permission. A PV inverter can be physically connected to a bus that a DG set energises. That alone does not establish that the inverter is allowed to parallel with the generator, that its output can be limited quickly enough, or that reverse power is prevented under a sudden load drop. The one-line needs device labels and references to a control narrative that settle those questions.
Show the utility incomer, changeover or transfer arrangement, DG breaker, PV AC breaker, main load bus, metering point, and any dedicated controller on the same logical diagram. If there are separate essential and non-essential buses, draw both and show where the PV injection sits. A solar connection on the wrong side of an automatic transfer switch can behave very differently from the arrangement assumed in a generic drawing.
| Operating state | Question the SLD must answer | Supporting document |
|---|---|---|
| Utility available | Can PV export, or is it constrained behind the meter? | Utility approval and export-control design basis |
| Utility lost | Does PV trip, remain off, or operate under an approved hybrid controller? | Inverter and controller compatibility record |
| DG started | Which source establishes the AC bus, and which breakers permit paralleling? | DG and switchgear sequence of operation |
| Load suddenly falls | What limits PV and protects the DG from reverse power? | Controller response, relay and generator data |
| Fault or control failure | Which device disconnects what, and how is the failure shown? | Protection study and fail-safe logic |
This table is a design review prompt, not a universal sequence of operation. Mark the actual supported states on the project drawing and refer to the approved controller narrative by revision.
Draw the source boundary before drawing the controller
Start with a source and load map. Draw the incoming utility, site transformer or service, generator, inverter outputs and each load bus. Give every switchboard and breaker an identifier that also appears on the equipment schedule. Mark normal-open and normal-closed positions if they are relevant to the sequence. A reviewer should be able to trace a path with a pencil without guessing which line is a bus coupler and which is a cable crossing.
Next, identify the point of common coupling and the DG protection boundary. These may not be the same location. A meter that measures power at the utility incomer can support a grid export limit, yet it may not measure reverse power into a generator on an isolated bus. Conversely, a meter on the DG feeder may show the generator’s real power but not prove compliance with a utility export condition. The SLD should show both measurement positions when both controls are part of the design.
Show current transformers (CTs), voltage sensing and communication links with enough detail to identify what each controller reads. A one-line can use dashed control lines so it remains legible; the dashed lines still need a legend, endpoint labels and a reference to the detailed wiring diagram. A controller icon floating near the switchboard with no CT location leaves the essential design question unanswered.
Mark whether a PV controller issues power-limit commands to inverters, opens a PV breaker, or does both. These actions have different timescales and consequences. If a hardwired permissive is used, identify its source and destination. If the scheme relies on network communication, indicate the network path and define the failure response in the control narrative. Do not choose a fail-safe state by copying a previous project: it must be coordinated with the actual inverters, DG protection and site load requirements.
Some manufacturer documents illustrate why the positions matter. SolarEdge’s power plant controller guide describes measuring active power at a grid connection point and commanding inverter output to enforce a dynamic export limit. That is a SolarEdge product configuration, not a generic approval for any PV + DG arrangement. Use the exact installed models’ current instructions when drawing a real scheme.
Synchronisation belongs in the operating-state note
The word synchronisation is often used loosely. On a one-line, say which sources may operate in parallel and under what permission. A utility-to-DG transfer that breaks before making a new connection is different from a closed-transition transfer. A PV inverter following a DG-formed bus is different from two generator sets synchronising with one another. The SLD must make these distinctions visible, while the detailed control narrative specifies the sequence and settings.
For each permitted parallel state, identify the source of voltage and frequency reference, the device that checks the permissive, and the breaker or contactor that closes. For each forbidden state, show the interlock or trip path that prevents it. If the utility and DG are not to be paralleled, the drawing should not leave an apparently closed path between them. If the design allows a transition overlap, the basis and approval need to be documented separately.
Ask the following questions during review. Does the PV inverter’s operating mode support the intended bus? Does the generator’s governor and voltage regulator tolerate the PV output variability and load steps considered? Does the control scheme curtail PV before the DG reaches a prohibited operating condition? What happens if the controller loses CT input, inverter communication or auxiliary power? Which event is latched, which resets automatically, and who checks the state after a trip?
The SMA Hybrid Controller manual is one manufacturer example of coordinating controller and genset reverse-power protection. It warns that a genset protection trip occurring before controller protection can produce an unexpected genset stop. This supports a general engineering lesson: the protection sequence must be coordinated, documented and tested. It does not supply settings for an unrelated controller or generator.
Put the approved sequence in a numbered note or a referenced control narrative. “PV operates with DG” is too vague for a commissioning team. A useful note identifies conditions such as DG breaker status, bus voltage present, metering healthy, control communication healthy and PV enable command. A second note should describe what disables PV. The SLD need not print every PLC rung, but it should show where the logic acts on the electrical system.
Zero export and DG minimum loading are different checks
Zero export usually describes a limit at a named boundary, commonly the utility connection. Minimum DG loading concerns the generator while it is running. They can be active in different operating states. A system can comply with a utility export limit and still drive power back towards the DG if a load falls while the generator is supplying the site. The SLD should not hide both under one box labelled “zero-export controller.”
Give each limit a name, measurement point, controlled device and failure response. For a utility export limit, show the utility-side metering and any contractual or approval basis. For DG protection, show the generator-side measurement and the reverse-power or minimum-load logic appropriate to the equipment. A controller may perform both functions, but the drawing should still distinguish them so a reviewer can test each one separately.
The DG minimum stable load is a manufacturer- and site-specific input, not a percentage to assume from an internet example. Obtain the DG make/model, operating manual, service condition and intended loading range. A generator may have its own protection relay and breaker logic. The PV controller’s response should be coordinated with those devices. If the EPC has no confirmed generator data, flag that as an open item and do not issue final controller settings.
An older SMA Fuel Save Controller technical note explains the practical concern: a sudden load step can make inverter power reduction too slow to avoid reverse power for a particular configuration. Its numerical response example belongs to that product and document date. The lesson for an SLD is to show where measurement, curtailment and hard protection sit, then prove the actual installed equipment’s response through engineering and commissioning.
| Control objective | Measurement point to draw | Output or protective action to identify | Test question |
|---|---|---|---|
| Utility export limit | Approved point of connection | Inverter curtailment and any required disconnect | Does a load drop create prohibited export? |
| DG reverse-power protection | DG feeder or defined generator boundary | Controller limit, reverse-power relay and breaker response | Is the genset protected before damaging backfeed persists? |
| DG minimum loading | DG power measurement | PV curtailment or dispatch adjustment | Does PV reduce before the DG operates below its specified range? |
| Loss of control signal | CT/VT input and controller health | Defined fallback or trip | Is the failure visible and safe for this site? |
The table lists engineering questions, not fixed relay values. Use the actual equipment manuals and a project-specific study to determine setpoints and timing.
Protection and interlocks to make visible
An SLD for a hybrid site should identify the protective devices and the interfaces between them. Show PV AC isolation, DG breaker and protection relay, utility incomer, transfer device, relevant bus couplers, and metering. Label protection functions in a legend or schedule with their device identifiers. If a relay function is represented by an ANSI number, verify that its exact use and setting are documented in the protection schedule rather than assuming the number alone explains the scheme.
Anti-islanding and loss-of-mains behaviour need a clear boundary. State whether the PV must disconnect when utility voltage is lost, or whether a separately engineered islanded operating mode exists. If islanded operation exists, show the source that forms the island, the isolation device that separates it from the utility, and the re-transfer permissive. Do not use “hybrid” as a substitute for those details. A battery-free PV and DG scheme may have a very different transient response from a battery-supported microgrid.
If emergency stop, fire-service isolation, or local shutdown controls are part of the project, show their electrical effect on the relevant breakers or inverters and refer to the detailed wiring diagram. Keep the SLD readable: a separate control schematic can carry terminal-level detail. The two documents must agree on device IDs and revision. The site team should be able to answer “what opens?” from the one-line and “which wire does it?” from the control schematic.
The current utility approval may impose a specific export, metering or protection arrangement. For Gujarat, the regulator lists 2026 distributed renewable energy regulations, notified 30 October 2026; an EPC should not copy a pre-2026 Gujarat application scheme into a new project without checking the transition rule and the relevant DISCOM’s instructions. This article does not make a Gujarat-specific eligibility or zero-export approval claim.
A drawing review sequence before issue
Review the package in a fixed order so a polished diagram does not conceal a missing operating state.
- Trace sources. Follow utility, DG and PV to each load bus in every permitted switch position. Mark any path that appears to parallel sources unintentionally.
- Trace sensors. Locate CTs, voltage measurements, DG status inputs and controller communication. Ask whether each controller actually sees the boundary it is meant to protect.
- Trace actions. Identify which inverter command, relay contact or breaker changes when export, reverse power or a fault condition occurs.
- Trace failures. Remove one signal at a time conceptually: CT, controller power, network, DG run status. The narrative should say what happens.
- Reconcile documents. Match inverter and DG models, breaker ratings, CT ratios, transformer details, bus names and drawing revisions to schedules and studies.
- Match the approval. Compare metering, export and protection arrangement with the current written utility or authority condition for the site.
Record unresolved items in a drawing comment log with a named owner and target revision. A typical open item is “DG minimum load not yet supplied by vendor.” That is more actionable than a general caveat saying “subject to site verification.” The EPC can then decide whether the drawing is fit for a bid discussion, approval submission or construction issue.
For basic drawing interpretation, use the solar SLD reading guide. For a broader electrical drawing package, see Heaven Designs’ electrical and CEIG drawings service. Name the project stage and intended reviewer when you ask for an SLD so the scope can be set against the right deliverables.
What to send with a solar + DG SLD enquiry
Send the existing electrical one-line, DG make/model and manual, PV module and inverter selections, load profile or measured demand, switchgear arrangement, transformer information, utility approval or application conditions, and any existing protection study. Include the normal and emergency operating states you want. If the site already has a DG set, provide the as-built drawing and actual breaker or relay details rather than relying on its nameplate alone.
State the issue purpose. A concept SLD for a tender can identify open design questions; an approval or construction issue needs resolved inputs and project-specific checking. If an export limitation or DG parallel mode is proposed, describe the intended boundary and recipient. If the generator must run during utility outages, state whether the PV is expected to stay on in that state. These decisions affect the drawing and the controls that must be evaluated.
Heaven Designs lists SLDs and related electrical documents among its solar engineering deliverables. Send the project details through the contact route to request a scoped engineering response. The team can reply with scope, price and a delivery date after reviewing the actual inputs. The SLD should remain a record of an agreed design, not a promise that any generic control scheme will work on every DG-backed site.