Before committing crores of rupees to a solar project, how do you know if the site is truly viable? A solar feasibility study answers that question before land, equipment or detailed engineering money is spent. This guide is for solar EPCs, developers and C&I buyers in India who need to commission, scope or review one.
Quick answer. A solar feasibility study is a preliminary assessment of a proposed solar site that tests land or roof suitability, shading and energy yield (P50/P90), grid connectivity, approvals and financial returns such as IRR and LCOE. It ends in a go, modify or no-go recommendation and comes before land purchase and detailed engineering.
The process, deliverables and financial checks below show what a complete solar feasibility report should contain and how it prevents expensive errors. For a faster first screen, see the 20-minute solar feasibility check.
TL;DR
- A solar feasibility study is a preliminary go/no-go assessment covering site suitability, energy yield, grid connectivity, and financial viability, distinct from construction-ready detailed engineering.
- A study moves through desktop analysis, site survey, technical modelling and report compilation; duration and fee depend on site size, access and data availability.
- Key components include site and land analysis, shading and energy yield modeling, and grid connectivity assessment, including substation distance and evacuation capacity.
- Deliverables include an executive summary, preliminary layouts, P50/P75/P90 energy estimates, financial metrics like IRR, NPV, and LCOE, and a risk assessment.
- Identifying constraints early, such as insufficient grid evacuation capacity or unsuitable soil conditions, routinely saves 5-20% of CAPEX in avoided rework or abandoned commitments.
- Choosing a provider with local Indian regulatory expertise and integrated feasibility-to-engineering services reduces risk and streamlines the transition to detailed design.
📖 Table of Contents
What Is a Solar Feasibility Study?
A solar feasibility study is a full preliminary assessment that evaluates whether a proposed solar project is technically viable, financially sound, and practically executable. Unlike detailed engineering design, which provides construction-ready drawings and specifications, a feasibility study answers the fundamental question: “Should we proceed with this project?”
For solar EPC companies in India, commissioning a feasibility study before investing in detailed engineering serves multiple critical purposes. It validates site suitability, estimates energy generation potential, assesses grid connectivity options, and provides preliminary financial projections. This early-stage analysis costs a fraction of full detailed engineering, yet it can save lakhs of rupees by identifying deal-breakers early.
The key distinction between a feasibility study and detailed design lies in depth and purpose. A feasibility study provides a high-level assessment with preliminary layouts and estimates, helping stakeholders make go/no-go decisions. Detailed engineering, on the other hand, delivers construction-ready documentation with precise specifications, structural calculations, and permit-ready drawings. Think of the feasibility study as the reconnaissance mission that determines if the battle is worth fighting.
If the opportunity has not reached full-study scope, start with the 20-minute solar feasibility check. It records site, resource, electrical, and commercial gaps without presenting desktop evidence as final feasibility.
In the project lifecycle, the feasibility study sits at the very beginning, immediately after initial site identification. It precedes land acquisition finalization, detailed engineering, procurement, and construction. This strategic positioning allows developers to abandon unsuitable sites before significant capital commitment, making it one of the most cost-effective risk mitigation tools available to solar EPCs.
Key Components of a Solar Feasibility Study
A full solar feasibility study encompasses multiple technical disciplines, each contributing essential data to the overall viability assessment. Understanding these components helps EPC companies know what to expect when commissioning studies and how to evaluate the thoroughness of deliverables.
Site Assessment and Land Analysis
The foundation of any feasibility study begins with detailed site assessment and land analysis. Engineers evaluate the total land area available and calculate usable space after accounting for setbacks, access roads, and unusable zones. For ground-mount projects in India, the general rule suggests approximately 4-5 acres per MW for fixed-tilt systems, though this varies based on terrain and layout optimization.
Terrain evaluation examines slope characteristics, as excessive gradients increase civil work costs and may render sites impractical. Most solar installations prefer slopes under 5 degrees, though steeper terrain can be accommodated with additional grading and foundation work. The feasibility study quantifies these requirements and their cost implications.
Access roads and existing infrastructure receive careful scrutiny. Sites must accommodate heavy equipment during construction and maintenance vehicles throughout the project’s 25-year lifespan. Remote locations may require significant access road development, impacting project economics. Environmental and ecological considerations, including protected species habitats, wetlands, and forest land classifications, are documented to identify potential regulatory hurdles.
Land ownership verification, while primarily a legal function, forms part of the site assessment. The study confirms whether land titles are clear, identifies any encumbrances, and notes if multiple parcels require consolidation. These factors directly impact project timeline and feasibility.
Shading Studies and Energy Yield Analysis
Shading analysis represents one of the most critical technical components of a solar feasibility study. Engineers conduct both near-shading analysis (from on-site obstacles like buildings, trees, or terrain features) and far-shading analysis (from distant mountains, tall structures, or vegetation). Advanced software tools simulate sun paths throughout the year, calculating shading losses for each hour of operation.
In India, where seasonal variations affect sun angles significantly, the feasibility study must account for monsoon cloud cover patterns, winter sun angles, and summer peak production periods. Shading losses can range from negligible (under 2%) for ideal sites to prohibitive (over 15%) for heavily obstructed locations. The study quantifies these losses and recommends mitigation strategies, such as selective tree removal or layout optimization.
Energy yield analysis combines solar resource data with shading calculations to project annual generation. Using historical irradiation data from sources like NASA POWER, NREL, or ground-based monitoring stations, engineers estimate the site’s solar potential. Performance ratio (PR) assumptions, typically 75-85% for well-designed systems in India, account for system losses including inverter efficiency, soiling, temperature effects, and transmission losses.
Grid Connectivity Assessment
Grid connectivity often determines project viability, particularly for utility-scale installations. The feasibility study identifies the nearest substation, measures the distance, and assesses available evacuation capacity. In many Indian states, grid congestion limits new solar connections, making this assessment critical.
Engineers evaluate appropriate voltage levels based on project size. Small rooftop systems typically connect at 415V or 11kV, while megawatt-scale projects require 33kV, 66kV, or 110kV interconnection. Each voltage level carries different technical requirements and cost implications, which the feasibility study outlines.
Interconnection cost estimation includes transmission line construction, substation upgrades if needed, and utility coordination expenses. For remote sites, these costs can exceed several crores, potentially rendering otherwise attractive sites economically unviable. The study provides preliminary cost ranges, allowing developers to factor these expenses into financial models.
Utility coordination requirements vary by state and distribution company (DISCOM). The feasibility study identifies the relevant utility, notes their interconnection policies, and estimates approval timelines. Some states offer streamlined processes, while others involve lengthy bureaucratic procedures that impact project schedules.
Solar Feasibility Study Process: Step by Step
Understanding the step-by-step feasibility study process helps EPC companies plan their project timelines and prepare necessary inputs. While specific methodologies vary among service providers, the fundamental workflow remains consistent across the industry.
The process begins with initial client consultation and requirement gathering. Engineers discuss project objectives, capacity targets, budget constraints, and timeline expectations. Clients provide available site information including location coordinates, land documents, any existing surveys, and preliminary project concepts. This phase establishes scope and ensures alignment between client expectations and deliverable content.
Next comes desktop analysis and preliminary assessment. Using satellite imagery, GIS data, and publicly available information, engineers conduct remote site evaluation. They analyze solar resource data, identify nearby substations, review topographical maps, and assess preliminary layout options. This desktop phase provides initial viability indicators before committing to site visits.
The site visit and data collection phase involves physical inspection by qualified engineers. Teams document site conditions through photographs and videos, verify land boundaries, identify obstacles and shading sources, assess soil conditions, and measure distances to key infrastructure. In India, site visits for ground-mount projects often reveal conditions not visible in satellite imagery, such as seasonal water logging, unauthorized encroachments, or access restrictions.
Following data collection, engineers proceed to technical analysis and modeling. Using specialized software, they create preliminary system layouts, run shading simulations, calculate energy generation estimates, and model different configuration options. This phase is the analytical heart of the feasibility study, where raw data becomes decisions.
Financial viability assessment translates technical findings into economic projections. Engineers estimate capital costs, project operational expenses, calculate revenue based on applicable tariffs or power purchase agreements, and compute key financial metrics. This analysis shows stakeholders whether the project should be built from a business perspective, as well as whether it can be built.
Finally, report compilation and presentation packages all findings into a full document. The report synthesizes technical analysis, financial projections, risk assessments, and recommendations into an executive summary suitable for decision-makers. Ask the provider to walk you through the findings in a review meeting.
Feasibility Study Timeline: What to Expect
For solar EPC companies planning project schedules, understanding typical feasibility study timelines helps coordinate subsequent activities. While duration varies based on project complexity and site accessibility, most studies follow a predictable timeline structure.
Duration is agreed at scoping because it depends on site count, terrain, data availability and grid complexity. What stays constant is the order of the four phases.
Desktop analysis comes first. Engineers gather satellite data, analyse solar resources, review available documentation and prepare for site visits, which moves fastest when clients provide complete initial information.
The site survey follows, and its length depends on site size, location and travel. An urban rooftop needs far less field time than a large, remote ground-mount site. For projects across India, our site survey and land feasibility service schedules surveys to keep this phase short.
Analysis and modelling is usually the longest phase. Engineers process collected data, create layouts, run simulation scenarios, perform shading analysis and build financial models.
Report preparation closes the study. Engineers compile findings, create visualisations, write recommendations and run an internal review before delivery.
Several factors can affect the feasibility study timeline. Site accessibility issues, such as monsoon flooding or restricted access, may delay site visits. Incomplete initial data requires additional information gathering. Complex grid connectivity scenarios involving multiple utilities or voltage levels extend analysis time. Client responsiveness for clarifications and approvals also impacts overall duration.
Understanding how timeline impacts project planning helps EPCs schedule subsequent activities. The feasibility study should be completed before finalizing land acquisition, as findings may reveal deal-breakers. It must precede detailed engineering procurement, since the study defines scope and system configuration.
What Does a Solar Feasibility Report Contain?
A full feasibility study report delivers multiple components, each serving specific decision-making needs. Understanding these deliverables helps EPC companies evaluate service provider proposals and ensure they receive complete analysis.
The executive summary provides a concise overview with a clear go/no-go recommendation. This section, typically 2-3 pages, summarizes key findings, highlights critical risks or opportunities, states recommended system capacity and configuration, and provides high-level financial metrics. Busy executives often read only this section, making its clarity and completeness essential.
Site layout and preliminary design deliverables include scaled site plans showing proposed panel placement, access roads, inverter locations, and electrical routing. While not construction-ready, these layouts demonstrate spatial feasibility and provide a visual reference for stakeholders. Many reports include 3D renderings or aerial visualizations that help non-technical stakeholders understand the proposed installation.
Energy generation estimates form the technical core of the feasibility study. Reports specify annual energy production in kWh or MWh, monthly generation profiles accounting for seasonal variations, performance ratio assumptions and loss calculations, and specific yield (kWh per kWp installed). These projections, typically provided with confidence ranges (P50, P75, P90), enable financial modeling and revenue forecasting.
Financial viability metrics translate technical performance into business outcomes. Key metrics include project IRR (Internal Rate of Return), NPV (Net Present Value), simple payback period, levelized cost of energy (LCOE), and return on investment over the project lifetime. The report should clearly state assumptions regarding capital costs, O&M expenses, tariff rates, and discount rates used in calculations.
Risk assessment and mitigation strategies identify potential project challenges and propose solutions. Common risks documented in Indian solar feasibility studies include grid curtailment possibilities, land acquisition complications, regulatory approval uncertainties, equipment availability and pricing volatility, and environmental or social concerns. For each identified risk, the report should suggest mitigation approaches and estimate probability and impact.
Technical specifications and equipment recommendations provide preliminary guidance on system components. While detailed equipment selection occurs during engineering design, the feasibility study recommends module types and wattages, inverter configurations (string vs. central), mounting structure approaches (fixed-tilt vs. tracking), and electrical architecture (AC vs. DC coupling for hybrid systems). These recommendations establish the baseline for subsequent detailed engineering.
Finally, the report outlines next steps and detailed engineering scope. It defines what additional work is required to move from feasibility to construction-ready design, estimates timelines for detailed engineering and permitting, identifies critical path activities, and may provide cost estimates for subsequent project phases. This roadmap helps EPCs plan resources and budgets for project advancement.
Financial Viability Metrics in Feasibility Studies
Financial analysis within a feasibility study determines whether a technically viable project makes business sense. Understanding these metrics helps EPC companies and their clients make informed investment decisions.
Capital expenditure (CAPEX) estimation provides preliminary project cost projections. For Indian solar projects in 2026, typical CAPEX is roughly ₹3.5-4.5 crore per MW for ground-mount systems and somewhat higher per MW for C&I rooftops, though costs vary based on location, scale, and specifications.
The feasibility study breaks down CAPEX into major categories: solar modules, inverters and electrical equipment, mounting structures, civil and foundation work, grid connectivity and transmission, and engineering, procurement, and construction margins.
Operational expenditure (OPEX) projections estimate ongoing costs throughout the project’s 25-year lifespan. Annual O&M typically ranges from 0.5-1.5% of CAPEX for well-maintained systems. Components include preventive and corrective maintenance, module cleaning (particularly important in dusty Indian conditions), security and site management, insurance premiums, land lease payments if applicable, and inverter replacements at 10-12 year intervals.
Levelized cost of energy (LCOE) calculations provide a standardized metric for comparing project economics. LCOE represents the per-unit cost of electricity generation over the project lifetime, accounting for all capital and operating expenses. In India, competitive solar projects achieve LCOE between ₹2.50-3.50 per kWh, depending on location, scale, and financing terms. The feasibility study calculates LCOE using standard formulas and compares it to applicable tariffs or grid electricity costs.
Return on investment (ROI) analysis examines profitability from multiple angles. Internal Rate of Return (IRR) indicates the discount rate at which NPV equals zero, with most Indian solar projects targeting 12-18% IRR depending on risk profile. Net Present Value (NPV) shows absolute profit in today’s rupees, helping compare projects of different scales. Equity IRR, relevant for leveraged projects, measures returns specifically on equity investment after accounting for debt service.
Payback period calculations indicate how quickly the project recovers initial investment. Simple payback, which doesn’t account for time value of money, typically ranges from 5-8 years for Indian solar projects. Discounted payback, which applies discount rates, extends to 7-10 years. These metrics help stakeholders understand liquidity and risk exposure timelines.
Sensitivity analysis tests how financial outcomes change when key variables fluctuate. The feasibility study typically examines sensitivity to module efficiency and degradation rates, tariff or power purchase agreement rates, debt interest rates and terms, O&M cost variations, and grid availability or curtailment scenarios. This analysis identifies which variables most significantly impact returns, guiding risk management focus.
How Feasibility Studies Prevent Costly Mistakes
The true value of a feasibility study often lies not in what it confirms, but in what it prevents. By identifying problems early, these studies save solar EPC companies from expensive mistakes that would only become apparent after significant investment.
Identifying site constraints before detailed engineering represents the primary value proposition. A thorough feasibility study reveals issues like excessive shading that would reduce generation below viable levels, soil conditions requiring expensive foundation solutions, flood zones or drainage problems affecting equipment placement, and inadequate land area for target capacity.
Discovering these constraints during feasibility, when only lakhs have been invested, prevents wasting tens of lakhs on detailed engineering for an ultimately unviable site.
Avoiding unsuitable locations early saves land acquisition expenses as well as engineering costs. Consider an illustrative scenario: an EPC identifies a 50-acre site for a 10 MW project, negotiates land lease terms, and is about to sign when a feasibility study shows the nearest substation has no evacuation capacity, with the next viable connection point 12 km away.
Transmission costs above ₹2 crore would wreck the project economics. A study costing under ₹2 lakh prevents the commitment.
Preventing grid connectivity surprises protects project timelines and budgets. In many Indian states, grid connection approvals involve complex bureaucratic processes and technical requirements that vary by utility. A feasibility study engages with relevant DISCOMs early, identifies specific requirements, estimates realistic approval timelines, and uncovers potential roadblocks like required substation upgrades or transmission line construction. This foresight allows accurate project scheduling and cost estimation.
Optimizing system sizing and configuration ensures projects are neither over-designed (wasting capital) nor under-designed (missing revenue opportunities). The feasibility study determines optimal capacity based on land constraints, grid connection limits, and financial returns. It evaluates trade-offs between fixed-tilt and tracking systems, assesses whether bifacial modules justify their premium cost, and determines ideal inverter loading ratios. These optimization decisions, made during feasibility, establish the foundation for efficient detailed engineering.
Two further illustrative cases show the pattern. A 5 MW rooftop program across seven industrial buildings finds that three roofs cannot carry the load without expensive reinforcement; redesigning for about 3.2 MW on the viable roofs avoids tens of lakhs in structural upgrades. A ground-mount site with seasonal waterlogging in one low-lying corner gets a revised layout and drainage plan, avoiding recurring equipment damage that would cost far more than the study.
The financial logic is simple. A feasibility study costs a small fraction of 1% of project CAPEX, yet it routinely finds issues that would cost several percent of CAPEX to fix later.
Feasibility Study Requirements for Indian Solar Projects
India’s state-by-state rules mean feasibility study requirements vary across states and project types. Understanding these variations ensures studies address all necessary compliance aspects.
State-specific regulatory requirements create a complex compliance environment. Some states mandate feasibility studies for projects above certain capacity thresholds, while others leave this to developer discretion. States like Gujarat and Rajasthan, with mature solar markets, have streamlined processes and clear guidelines. Emerging markets like Bihar or Jharkhand may have less defined requirements, requiring more extensive regulatory research during the feasibility study.
MNRE guidelines and compliance establish national-level standards, particularly for projects seeking central government subsidies or incentives. The Ministry of New and Renewable Energy (MNRE) specifies technical standards for system design, equipment specifications, and performance expectations. A thorough feasibility study verifies compliance with these guidelines, ensuring projects remain eligible for applicable incentive schemes.
Environmental requirements depend on location. Solar PV is not listed in the EIA Notification 2006, so central environmental clearance is generally not needed, but forest land, protected areas, coastal zones and lender standards can still require assessments. The feasibility study identifies whether environmental clearances are needed, estimates the approval timeline (which can extend 6-12 months), and flags potential environmental concerns that might complicate approvals.
Land use regulations across Indian states impose different restrictions on solar development. Agricultural land conversion requires specific approvals in most states, with varying difficulty and timelines. Some states restrict solar development in certain zones or require minimum distances from residential areas. The feasibility study researches applicable land use regulations and confirms the proposed site complies or identifies required approvals.
Grid code compliance requirements dictate technical specifications for grid-connected systems. State electricity regulatory commissions publish grid codes specifying voltage and frequency operating ranges, power quality requirements, reactive power capabilities, and protection and metering standards. The feasibility study ensures the proposed system design can meet these technical requirements, preventing costly redesigns during detailed engineering.
Documentation needed for project approvals varies by jurisdiction but typically includes land ownership documents, site survey reports, single-line diagrams, technical specifications, and financial viability assessments. The feasibility study identifies exactly which documents are required for the specific project location and type, allowing EPCs to begin preparation early. This proactive approach prevents approval delays that could jeopardize project timelines or financing commitments.
Choosing the Right Partner for Your Feasibility Study
Selecting a qualified service provider for your feasibility study significantly impacts the quality and usefulness of deliverables. Several key factors distinguish exceptional providers from mediocre ones.
Essential qualifications and experience form the foundation of provider evaluation. Look for teams with qualified engineers holding relevant degrees in electrical, civil, or renewable energy engineering. Professional certifications, while not mandatory, indicate commitment to industry standards. Most importantly, assess their track record with similar projects. A provider with extensive experience in ground-mount projects may lack expertise in complex rooftop installations, and vice versa.
Local expertise matters in India. India’s solar market presents unique challenges including diverse climatic conditions from Rajasthan’s deserts to Kerala’s monsoon regions, varying state regulations and utility practices, soil conditions and seismic zones affecting structural design, and local equipment availability and pricing.
Providers with deep India experience (Heaven Designs states a team of 50+ engineers in Surat and Ahmedabad) understand these differences.
Technology and software capabilities directly impact analysis quality. Advanced providers use industry-standard tools like PVsyst or Helioscope for energy modeling, AutoCAD or similar platforms for layout design, financial modeling software for economic analysis, and GIS tools for site analysis and mapping. Ask potential providers which tools they use and request sample outputs to judge their depth.
Track record and portfolio evaluation provides insight into provider capabilities. Request case studies or references from similar projects, review their portfolio for diversity and scale of completed studies, and ask about their success rate (what percentage of studied projects proceeded to construction). Providers who have completed many feasibility studies bring pattern recognition that less experienced teams lack.
Turnaround time and responsiveness matter for time-sensitive projects. Clarify standard delivery timelines and whether expedited options exist, assess their communication practices during the study process, and evaluate their willingness to accommodate your specific scheduling needs. Agree the timeline at scoping so it fits land negotiation deadlines and financing commitments.
Integration with detailed engineering services offers significant advantages. Providers who offer both feasibility studies and detailed engineering design carry assumptions straight through to construction-ready documentation. They maintain consistency in assumptions and approaches, reduce the learning curve for detailed engineering, and often offer package pricing that reduces overall project costs. Heaven Designs offers this integrated range of services, from initial feasibility through detailed engineering, PMC and structural design.
Frequently Asked Questions About Solar Feasibility Studies
What is the cost of a feasibility study? Cost varies with project size, complexity, site access and how much grid analysis is needed. A multi-site portfolio or a site needing evacuation studies costs more than a single rooftop. Ask providers for a scoped quote that lists exactly which deliverables are included.
How long does a feasibility study take? Duration depends on site accessibility, data availability, grid analysis complexity and how quickly clarifications are answered. Agree the timeline at scoping, and make sure the study finishes before land or financing deadlines.
What happens after the feasibility study? If the study recommends proceeding, the next step is typically detailed engineering design. This phase produces construction-ready drawings, specifications, and documentation. Simultaneously, EPCs often finalize land acquisition, begin equipment procurement processes, and pursue regulatory approvals.
If the study identifies significant concerns, stakeholders may decide to abandon the site, negotiate better terms based on identified issues, or modify the project scope to address constraints. The feasibility study provides the data foundation for these strategic decisions.
Can feasibility studies be done remotely? Partial remote analysis is possible using satellite imagery, GIS data, and publicly available information. However, complete feasibility studies require physical site visits to verify ground conditions, identify obstacles not visible in satellite images, assess access and infrastructure, and collect accurate measurements.
Remote-only studies may miss critical details that affect project viability. Reputable providers always include site visits as part of thorough feasibility assessments, though desktop analysis can provide preliminary insights before committing to full studies.
What data do I need to provide? To facilitate efficient feasibility studies, prepare the following information: site location coordinates or address, land ownership documents and area measurements, any existing site surveys or topographical data, target project capacity or available roof/land area, grid connection preferences or constraints, project timeline and key milestones, and budget parameters or financial expectations.
More complete initial data enables faster, more accurate studies. However, professional service providers can work with minimal information and gather additional data during the study process.
How accurate are feasibility study projections? Feasibility studies provide preliminary estimates with typical accuracy ranges of ±10-15% for energy generation projections, ±15-20% for capital cost estimates, and ±20-25% for financial metrics like IRR and payback period. These ranges reflect the preliminary nature of feasibility analysis, which uses industry-standard assumptions rather than detailed engineering calculations.
Accuracy improves significantly during detailed engineering when precise equipment specifications, detailed layouts, and firm pricing are established. Despite these ranges, feasibility studies reliably identify whether projects fall into viable, marginal, or unviable categories, which is their primary purpose.
Take the First Step Toward Solar Project Success
A full feasibility study represents the foundation of successful solar project development. By investing a fraction of total project costs upfront, solar EPC companies across India gain the critical insights needed to make informed decisions, avoid costly mistakes, and optimize project design before committing significant capital.
From detailed site assessment and shading analysis to grid connectivity evaluation and financial viability metrics, a thorough feasibility study addresses every dimension of project viability. It identifies deal-breakers early, when walking away costs thousands rather than lakhs. It optimizes system configuration to maximize returns. And it provides the data-driven foundation that detailed engineering, financing, and construction planning require.
For solar EPCs dealing with India’s varied regulations and site conditions, an experienced feasibility partner makes the difference between projects that succeed and those that struggle.
Whether you are evaluating a rooftop installation in Mumbai, a ground-mount project in Rajasthan, or a multi-site commercial development, do not let the project proceed on assumptions.
To scope a feasibility study, contact Heaven Designs at service@heavendesigns.in or call +91 90811 00297 to discuss your project requirements and receive a customized proposal. Your successful solar installation begins with the right feasibility foundation.
FAQ
What is a solar feasibility study?
A solar feasibility study is a preliminary assessment of whether a solar project should go ahead. It checks the site, shading and energy yield, grid connection, approvals and financial returns, then ends with a go, modify or no-go recommendation before land purchase or detailed engineering.
What should a solar feasibility report include?
A solar feasibility report should include an executive summary, a preliminary layout, P50 and P90 energy estimates, a grid connectivity assessment, financial metrics such as IRR, NPV and LCOE, and a risk register. Each assumption should name its data source and date.
What is the difference between a P50 and P90 energy estimate in a solar feasibility study, and which should EPCs use for financial modelling?
P50 represents the energy generation level that the site is expected to exceed in 50 percent of years, essentially the median projection. P90 represents the generation level exceeded in 90 percent of years, a more conservative estimate that reflects unfavourable but not extreme weather variability.
For EPCs presenting business cases to clients, the P50 estimate is the appropriate central case to demonstrate expected returns. For projects seeking debt financing, lenders typically use the P90 estimate to confirm that even in a below-average solar year, the project generates enough revenue to service debt obligations.
The difference between P50 and P90 in Indian solar conditions typically ranges from 5 to 10 percent of annual generation, depending on location variability. Projects in Rajasthan and Gujarat with stable, predictable solar resources have tighter P50 to P90 spreads than projects in higher-variability monsoon-affected locations.
EPCs should request both figures from their feasibility study provider and present P50 in commercial proposals while stress-testing financial models against P90 to confirm project viability under unfavourable weather conditions.
Can a solar feasibility study be used directly to secure project financing, or does it need to be supplemented by additional technical due diligence?
A feasibility study provides the foundation for financing discussions but typically needs supplementation before lenders will commit funds. Banks and financial institutions funding MW-scale solar projects in India generally require an Independent Technical Advisor or Independent Engineer review, which is a third-party assessment of the feasibility study’s methodology, assumptions, and conclusions.
The ITA review verifies that irradiation data sources are appropriate, energy yield models are correctly configured, equipment specifications are sound, and grid connectivity assessments are credible.
For projects above approximately 10 MW or those seeking debt-to-equity ratios above 70 percent, lenders may also require P90 yield reports produced in PVsyst specifically. The feasibility study itself strengthens the financing application by demonstrating that risks have been identified and quantified, but it is the ITA sign-off on the study’s technical rigour that gives lenders sufficient confidence to approve credit.
Commissioning a feasibility study from a reputable engineering firm with established credibility in the project finance community reduces the ITA review time and the likelihood of adverse findings.
How should an EPC account for grid curtailment risk in the financial model of a solar feasibility study?
Grid curtailment, where the grid operator instructs a solar plant to reduce or halt generation due to local grid congestion or excess power, is a real risk in several Indian states, particularly in regions with high solar penetration such as parts of Rajasthan, Tamil Nadu, and Andhra Pradesh.
Feasibility studies should address curtailment risk by reviewing the DISCOM’s historical curtailment data for the local feeder, assessing the substation’s existing solar connection share relative to total load, and reviewing the state’s renewable energy curtailment policy regarding compensation.
The financial model should incorporate a curtailment scenario showing the impact of five, ten, and fifteen percent annual generation curtailment on project IRR. Where curtailment risk is high, the study should evaluate whether a must-run status or curtailment compensation mechanism exists under the power purchase agreement or regulatory framework.
Projects that proceed without curtailment risk assessment can experience generation losses of 10 to 20 percent in congested zones, which can reduce IRR below acceptable levels for investors who funded the project based on uncurtailed yield projections.
What site conditions automatically disqualify a location from solar project development, and should an EPC still commission a full feasibility study?
Certain conditions render a site fundamentally unviable regardless of other positive attributes: location within a notified protected forest requiring Forest Conservation Act clearance, active flood plain classification as a flood zone by revenue authorities with no engineering mitigation possible, zero grid evacuation capacity within 15 kilometres with no planned substation upgrades, land with unresolvable title disputes or government acquisition notifications, and sites falling entirely within CRZ-I ecologically sensitive areas.
When any of these absolute disqualifiers are confirmed during preliminary desktop research, a full feasibility study cannot convert the site into a viable project and its expense is not justified.
A preliminary desktop assessment is usually sufficient to identify these red-flag conditions using satellite imagery, government land records, forest department maps, and DISCOM published data.
However, apparent disqualifiers sometimes prove resolvable: a transmission line upgrade already in the DISCOM’s capital plan, a land boundary dispute limited to a portion of the site, or a flood zone classification affecting only low-lying portions. When any doubt exists about whether a disqualifier is absolute or potentially manageable, commissioning a targeted feasibility study to evaluate the specific constraint is worthwhile before abandoning the site.
How does a solar feasibility study for a rooftop project differ from one for a ground-mount project?
Rooftop feasibility studies are generally faster and lower cost than ground-mount studies because several complex components are either simplified or eliminated. Rooftop studies typically do not require geotechnical investigation since foundations are not driven into soil, land ownership verification is simpler since it is the building owner’s property, and environmental clearance assessment is minimal since no land conversion is involved.
However, rooftop studies require a structural integrity assessment that ground-mount studies do not: the engineer must confirm the existing building can carry the additional panel and mounting load, which may involve reviewing structural drawings, conducting visual inspections, or ordering non-destructive testing for older buildings.
Ground-mount feasibility studies involve more extensive civil engineering assessment of terrain, drainage, access roads, and soil conditions. They also require more detailed grid connectivity analysis because the projects tend to be larger and connect at higher voltage levels.
Regulatory research is more extensive for ground-mount projects due to land use conversion requirements, potential environmental clearance thresholds, and in some cases agricultural land restriction policies. The typical cost and timeline for a rooftop feasibility study is roughly 40 to 60 percent of what a comparable-capacity ground-mount study requires.