An AC cable schedule for a “1 MW solar plant” starts by identifying what 1 MW refers to and where the cable sits. A 1 MW AC output at 415 V implies a very different current from the same power at 11 kV. The engineer must also know whether the run is a single inverter feeder, an aggregate LT collector, a transformer connection or an HT evacuation line. Current alone does not select a cable: installation method, temperature, grouping, route length, voltage drop, fault level, protection, conductor construction, jointing and utility requirements can all control the result.

Quick answer. For a declared 1,000 kW three-phase AC example at unity power factor, the arithmetic current is about 1,391 A at 415 V and 52.5 A at 11 kV, using I = P/(√3 × V × PF). These are illustrative line currents, not cable sizes. A real schedule must use the specified maximum continuous duty and chosen equipment, calculate corrected ampacity for the cable’s installation, then check voltage drop and short-circuit withstand. Do not compare the two currents as if the LT and HT cables were interchangeable.

Fix the electrical boundary before calculating current

“1 MW plant” might be 1 MWp of PV modules with 800 kW of inverter output, 1 MW of inverter AC nameplate, or 1 MW permitted export after transformer and auxiliary losses. This article assumes 1,000 kW AC at the point under discussion solely to show the current calculation. It does not imply that a 1 MWp DC plant has 1 MW AC output. For a real job, the SLD and equipment schedule must state the inverter ratings, transformer ratio, export limit, power factor operating range and all simultaneous sources. The AC collector could carry less or more than a casual “1 MW” label suggests, depending on topology and contractual definition.

The circuit location matters. Four 250 kW inverters might have four separate low-voltage feeders. Those feeders can meet at an AC collection board, which then feeds a transformer. The transformer secondary may be 11 kV, with an HT cable to the utility point of connection. Each segment has its own current, installation method, fault exposure and protection device. A BOQ that lists one “1 MW AC cable” line without from/to tags cannot be sized or priced correctly. The voltage level is a design input, not something to infer from the plant size alone.

An EPC should create a route register before choosing sections. Record inverter-to-board, board-to-transformer and transformer-to-grid segments separately. For each, identify nominal voltage, conductor material, number of cores or single-core formation, run length, installation environment, expected maximum current and protective device. Add whether the segment is in a covered tray, open air, conduit, trench or buried duct. Where a route changes environment, the thermal checks may need separate segments even if the same cable continues through them.

SegmentExample roleCurrent basisOther data needed
Inverter AC feederOne inverter to collectorExact inverter maximum AC currentCable route, breaker, termination and ambient
LT collection feederCollector to transformerCoincident inverter output/design dutyParallel runs, fault level and transformer input
HT feederTransformer to grid pointTransformer output and utility conditionVoltage, protection, CT-PT, route and utility spec

This is a topology map, not a statement that every 1 MW installation has these three segments.

Worked current calculation, with assumptions visible

For a balanced three-phase circuit, active power is P = √3 × VLL × I × PF, where P is watts, VLL is line-to-line volts, I is line current in amperes and PF is power factor. Rearranging gives I = P/(√3 × VLL × PF). The expression is electrical arithmetic. It does not include transformer losses or inverter auxiliary duty unless the chosen P already represents the power at that location. It also assumes balanced phases and sinusoidal conditions for this teaching example; engineering selection should use the actual equipment and utility requirements.

At 1,000,000 W, 415 V line-to-line and PF 1.00, I = 1,000,000/(√3 × 415 × 1.00) ≈ 1,391 A. At 11,000 V and PF 1.00, I ≈ 52.5 A. If the plant is required to operate at PF 0.95 while delivering the same 1,000 kW of active power, current rises to about 1,464 A at 415 V or 55.2 A at 11 kV. The calculation shows why the operating power-factor requirement belongs in the design basis. The numbers are not an instruction to choose a cable with exactly that catalogue rating: continuous-duty, thermal, short-circuit and margin rules still apply.

CasePVLLPFI = P/(√3 VLL PF)
LT, unity PF1,000,000 W415 V1.001,391 A
LT, PF 0.951,000,000 W415 V0.951,464 A
HT, unity PF1,000,000 W11,000 V1.0052.5 A
HT, PF 0.951,000,000 W11,000 V0.9555.2 A

Values are rounded; √3 ≈ 1.73205. This table is an illustrative comparison, not a cable schedule. A transformer and network protection scheme can make the practical current basis different at each end. If the inverter manufacturer specifies a maximum AC output current that exceeds the simple nameplate equation, use the appropriate design current and document why.

Corrected ampacity, not catalogue ampacity

The next check asks whether the proposed cable can carry the design current under the actual conditions. A catalogue table is tied to a reference ambient, installation method, conductor temperature and formation. A cable in a ventilated tray may have a different rating from one in a buried duct or a tightly grouped set of parallel circuits. For a 1,391 A LT collector, multiple parallel cable sets may be needed. Their current sharing is not automatically equal: lengths, conductor material, terminations, route geometry, spacing and impedance must be coordinated. A designer should not simply divide 1,391 by a catalogue ampacity and round up without checking the parallel arrangement.

The IEC 60287-1-1:2023 standard describes steady-state cable current rating for AC systems in air, ducts, buried installations and other conditions. It recognises that conductor and insulation construction, surroundings and agreed operating limits matter. The IEC 60364-5-52:2009 + Amendment 1:2024 concerns selection and erection of wiring systems and addresses voltage-drop and installation issues. An Indian project should use the relevant adopted Indian/IEC standard, manufacturer data and utility specification named in its design basis, with the exact edition. This article uses those primary source descriptions to explain the checks; it does not claim a universal ampacity factor.

Temperature correction is only one part. A cable on a tray in a hot inverter room may be thermally limited even if it has a short length. A buried HT cable can be limited by soil thermal resistivity, burial depth, proximity to other circuits or duct arrangement. A long cable run can be constrained by voltage drop even if ampacity passes. The engineer must assess the worst segment and not use the most favourable table row for the whole route.

Rating inputLT questionHT question
Cable constructionMulti-core or single-core parallel sets?Insulation class, screen and armour?
AmbientRoof, room, tray temperature?Soil temperature and thermal resistivity?
GroupingHow many loaded circuits share a tray?How close are buried/duct circuits?
InstallationTray, conduit, enclosed riser?Direct buried, ducts or trench?
TerminationsLug, gland, switchgear temperature limit?Joint and termination kit rating?

Record the actual catalogue row and every correction factor on the calculation sheet. A bare “derating 0.8” cell without provenance cannot be audited.

Voltage drop and loss along LT and HT runs

Thermal capacity answers whether the cable can carry current within its temperature rating; voltage drop asks how much voltage is lost along the route. In a balanced three-phase AC circuit, a common engineering expression is ΔV ≈ √3 × I × L × (R cosφ + X sinφ), when L is the one-way route length in compatible units and R and X are per-unit-length conductor resistance and reactance at the relevant operating conditions. The source of R and X must be the selected cable and formation. This expression is a model for a simple balanced circuit; the engineer must account for actual network topology and the project limit.

For comparison, suppose an LT collector carries approximately 1,391 A over a hypothetical 100 m route. Its drop cannot be calculated from current and length alone: a conductor size, material, number of parallel runs, temperature and cable formation are missing. Making up a 1% result would look precise but be false. An HT route carrying about 52.5 A over the same distance is likely to have a different drop, but it too needs the exact cable parameters and network study. The high-voltage cable also has different insulation and fault requirements. A low current is not permission to choose the smallest available HT cable.

Loss is another decision input. For a balanced three-phase run, resistive loss is approximately 3 × I² × Rphase at the operating point. For parallel sets, current sharing and effective resistance must be assessed. The calculation can inform an economic trade-off between cable cost and lifetime losses, but it should use a realistic load profile rather than assume 1 MW output all year. A fixed annual generation or savings number does not follow from the cable equation. If the tender specifies a maximum voltage drop or loss, cite that source and check it at the relevant design condition; do not invent a universal India-wide limit.

For long routes, an EPC can compare two cable options with a transparent table: conductor size, corrected ampacity, voltage drop at design current, losses over a stated profile, installed cost, trench or tray changes and fault rating. The cheapest conductor price is not necessarily the cheapest installed or operating circuit. The calculation must still pass the minimum safety and utility requirements before a lifecycle comparison is meaningful.

Short-circuit, protection and HT interface checks

An AC cable must withstand the prospective fault current until its protective device clears. The fault level and clearing time come from the electrical network and protection study, not the plant’s 1 MW nameplate. The cable conductor, screen, armour and terminations may each have a relevant short-circuit duty. The EPC should request utility fault data and existing switchgear information, then verify the selected cable against the worst credible duty and protection settings. For an HT evacuation feeder, the interface with the utility relay scheme and meter/CT-PT arrangement must also be fixed.

The CEA construction standards register lists the 2022 rules and later amendments. The CEA safety regulations register lists the 2023 safety regulation and later amendment. Those registers show why a 2020 spreadsheet should not be treated as a timeless design authority. The engineer should record the currently applicable editions and jurisdictional conditions in the project file. This guide does not assert compliance of any proposed cable because no cable, fault study or grid approval has been supplied.

Protection coordination also affects cable selection. A circuit breaker or relay that trips too slowly under a fault can make an otherwise adequate conductor fail a thermal-withstand check. Conversely, a cable uprating may not solve an incorrect protection scheme. The designer should align the SLD, cable schedule and relay-setting study. If an AC collector has multiple inverter feeders, ensure every feeder’s isolation and labelling are clear. If an HT line is utility-owned, the EPC scope may stop at the metering cubicle or a specified termination. Ownership should be shown on the SLD and BOQ so no cable length, joint or test is lost between contracts.

Commissioning adds practical checks: insulation and continuity tests, phase identification, termination records and as-built route documentation. A cable calculation based on one route should be revisited if the actual trench detours substantially. The procurement schedule should state spare length and joint policy explicitly; hiding a 10% allowance inside a base measurement makes later disputes hard to resolve.

Build a cable schedule that can be checked

The deliverable is more useful than a single size answer. Give each circuit a from/to ID, voltage, design current, cable construction, conductor area, number of parallel runs, route length, installation method, base rating, correction factors, corrected rating, voltage drop, short-circuit withstand basis, protective device, source data and revision. Separate LT and HT segments. Provide a plan showing where the route changes environment or crosses another service. Where the current route is preliminary, mark the calculation status and list what the site survey or utility must confirm.

  1. Confirm whether 1 MW is DC, inverter AC or export capacity.
  2. Draw the actual topology and assign segment IDs.
  3. Calculate each segment’s maximum duty from equipment and operating requirements.
  4. Choose candidate cable construction from the project specification and utility rules.
  5. Correct ampacity for each installation segment and parallel formation.
  6. Check voltage drop and losses with cable-specific R and X.
  7. Check fault withstand, protection, terminations and installation feasibility.
  8. Put the chosen cable and open inputs into a drawing-linked schedule and BOQ.

The existing general solar cable sizing guide explains the broader method. This 1 MW example makes the LT/HT difference and the missing design inputs visible. For a real project, send the SLD, inverter and transformer data, utility connection offer, route survey and fault information through the existing contact form. The firm can then reply with scope, price and a delivery date; turnaround is agreed at scoping.

Can I use one cable size for every 1 MW plant?

No. The voltage, circuit location, route, ambient, fault level, utility connection and equipment differ. The same 1 MW active power is about 1,391 A at 415 V but about 52.5 A at 11 kV at unity power factor. The cable insulation, construction and safety checks differ just as much as current.

Is the 11 kV cable automatically small because current is low?

No. Insulation voltage, minimum utility specification, screen and armour, fault duty, installation and terminations can control size. An HT cable is not a scaled-up LT cable. The utility interface and protection study must be reviewed.

How many parallel LT runs are needed?

That cannot be answered from the 1,391 A example alone. Obtain a candidate cable’s corrected ampacity for the actual installation, then check current sharing, voltage drop, short-circuit and terminations. Dividing by a free-air catalogue rating without grouping correction can understate the required number.

What is the acceptable voltage drop?

Use the project specification, applicable adopted standard and utility conditions. The calculation needs the chosen cable’s resistance and reactance, length and power factor. This article does not invent a universal percentage for all Indian solar AC feeders.

Should cable losses be capitalised into the choice?

They can be compared after each option passes safety and connection requirements. Use an operating profile and dated price assumptions, not a flat 1 MW output across 8,760 hours. State what is included in installed cost and who pays for the losses.

Sources checked 23 November 2026. All four current values are arithmetic examples from stated active power, voltage and power factor; none is a final cable selection.