This is an illustrative 1 MWp DC ground-mount take-off for an Indian EPC. It is a method and a worked quantity register, not a design for a real site or a price quote. The module wattage, string length, table geometry, inverter arrangement and cable routes below are declared assumptions so you can see exactly how each number is derived. Replace them with approved equipment data, survey distances, soil information, electrical calculations and the actual tender scope before issuing a procurement or construction BOQ.

Quick answer. Start a 1 MW solar power plant BOQ by fixing whether “1 MW” means DC module capacity or AC inverter capacity. For the 1,000 kWp DC example below, 1,600 assumed 625 Wp modules form 64 assumed strings of 25 modules. That arithmetic determines only module and string counts. Mounting steel, piles, cable, inverter, transformer, HT equipment, earthing, civil works and testing quantities need separate design inputs and are never safe to copy as universal “per MW” numbers.

Define the capacity and procurement boundary first

An EPC can lose more money from an ambiguous scope than from a wrong multiplication. “1 MW solar plant” may refer to 1 MWp of installed module nameplate DC, 1 MW AC at the inverter output, or a contracted export limit. Those are not interchangeable. The DC-to-AC ratio is a design decision driven by yield modelling, equipment, climate, grid and tender rules. This article takes 1,000 kWp DC as the example boundary and assumes 800 kW AC of inverter nameplate capacity, yielding a DC/AC nameplate ratio of 1.25. The ratio is arithmetic, not a performance claim or recommended design. If the tender instead requires 1 MW AC, re-run the entire module, inverter and balance-of-system schedule.

Next define what the EPC is buying. A BOQ can cover supply only, supply plus installation, or a complete EPC package including design, permits, testing and operation. Owner-supplied modules must not be priced again as contractor-supplied equipment, but the contractor may still need receiving inspection, unloading, storage, handling, installation, wastage and replacement allowances. A transformer or evacuation line can sit with a utility, the developer or the EPC depending on the point of connection. State that boundary in the first sheet and use a separate responsibility column for every line. “Included” without an owner is not a quantity.

An official SECI ground-mount balance-of-system tender identifies mounting structure, string combining/isolation arrangements, solar cables, connectors, conduits and power conversion units as distinct scope elements. That is a useful check against an abbreviated module-and-inverter shopping list. It is a tender example, not a standard design for a 1 MW site. The NREL 2022 US ground-mount cost study likewise separates site preparation, trenches, foundations, mounting, DC work, AC work and transmission. Its categories help check the completeness of a register; its US prices and assumptions do not set Indian quantities.

Basis itemIllustrative valueBasis statusWhat replaces it on a real job
Module capacity625 Wp eachAssumption, no model namedSelected module data sheet and approved procurement list
Installed DC capacity1,000,000 WpWorked example definitionTender’s DC requirement and final layout
Inverter AC capacity4 × 200 kW = 800 kWAssumption, no model namedApproved inverter schedule and grid conditions
Modules per string25Arithmetic assumption onlyCold/hot voltage and MPPT current checks using exact models
Modules per table16Layout assumption onlyApproved GA, structure and shading design
Site and evacuationUnspecifiedOpenSurvey, geotechnical report and interconnection agreement

The example intentionally does not claim a valid series string voltage, a safe pile count or a sized cable. Those need engineering checks before procurement.

DC-side line items: modules, strings and connectors

The module count is the one quantity that can be calculated directly from a declared capacity and module rating. Divide 1,000,000 Wp by 625 Wp per module to get 1,600 modules. Multiplying 1,600 by 625 gives exactly 1,000,000 Wp. If the selected module were a different rating, both the quantity and the resulting installed DC capacity would change. A BOQ should carry the actual model, wattage tolerance, certification requirements, delivery unit and spare treatment from the purchase specification. A percentage “module loss” added without a contract basis can conceal whether replacements are included, owner-supplied or payable separately.

For this demonstration, 25 modules are placed in one string: 1,600 ÷ 25 = 64 strings. This is a counting example, not an approved electrical string design. The exact module’s open-circuit voltage at the lowest design temperature, operating voltage at high temperature, inverter DC maximum voltage, MPPT window and input-current limits must all be checked. A 25-module string that is arithmetically convenient may be electrically impossible for a chosen inverter. If the valid string length is 24, the array layout and DC capacity need to be revisited rather than forcing a 25-module drawing to make the BOQ neat.

List module connectors and mating parts separately from bulk DC cable. Some connectors are factory fitted to module leads and some are required for field extensions or string home runs. Never count a replacement connector on every module simply because there are 1,600 modules. The correct number comes from the wiring diagram, table layout, termination method and manufacturer’s compatible connector instructions. The same principle applies to string fuses, isolators, surge protective devices and combiner boxes. A string inverter topology may use direct inverter inputs; a central inverter topology may use string combiner boxes. The SECI scope example explicitly distinguishes SCB and string-isolation arrangements according to topology. Decide the electrical architecture before assigning a box count.

DC itemIllustrative quantity or ruleUnitRelease condition
PV modules1,600eachConfirm exact 625 Wp model and tender eligibility
DC strings64stringVerify 25-module electrical string against selected equipment
Factory module leadsIncluded only if vendor supply specifiessetCheck procurement boundary
Field connectors and branch fittingsFrom string routing drawingeach/pairCheck mating compatibility and actual terminations
String fuse/isolator/combinerFrom protection architectureeachConfirm topology and device ratings
DC home-run cableFrom measured route × conductors × allowanceconductor-metreVerify size, insulation, route, losses and protection

A BOQ is more useful when every provisional entry has a measurable rule and a release condition. “Lump sum DC accessories” may be appropriate under a genuine turnkey contract, but the EPC should still have an internal take-off behind it.

Worked DC cable take-off with units

Cable is often where a generic per-MW rate becomes misleading. String positions, inverter location, trench route, table orientation, cable tray and segregation determine lengths. Suppose, strictly for illustration, that each of the 64 strings has a 35 m route from its string termination to its designated DC collection point, with two separate conductors. The measured conductor length is 64 strings × 35 m/string × 2 conductors = 4,480 conductor-metres. Add an explicitly assumed 8% procurement allowance for routing, termination and cutting: 4,480 × 1.08 = 4,838.4 conductor-metres. A purchasing schedule might round that to 4,850 conductor-metres, subject to reel planning and separate positive/negative colours. The allowance is an example, not an industry requirement.

This calculation does not size the cable. Current rating, ambient and grouping derating, route installation method, voltage drop, insulation voltage, short-circuit withstand, connector suitability and protection must be checked. It also does not count a separate trunk from a combiner to an inverter, because the example has not specified whether a combiner exists. If the actual layout has 20 m and 80 m string routes, using a single 35 m average may understate the long runs and distort voltage-drop checks. Use a route schedule with each segment identified and measured. For underground sections, trench length, duct length and cable length are different units: one 100 m trench may contain several 100 m cable runs.

For an AC feeder example, suppose each of four inverters has a 90 m route to an AC collection board. That is 360 route-metres. With a hypothetical 5% purchasing allowance it is 378 route-metres of each specified cable run. This says nothing about cable core count or parallel runs. A 3-core cable is normally purchased by route length, while individual single-core conductors may require three phase runs plus neutral or protective conductor as designed. The BOQ must state the actual cable construction and unit before multiplying. Mixing conductor-metres with route-metres in one row is a classic source of a large quantity error.

Example calculationFormulaResultExplicit exclusion
DC home-run conductors64 × 35 m × 24,480 conductor-mCable sizing and additional combiner trunks
DC purchase allowance4,480 × 8%358.4 conductor-mNot a mandated wastage rate
DC illustrative purchase4,480 + 358.4, rounded4,850 conductor-mReel optimisation and actual route changes
AC feeder route4 × 90 m360 route-mCore count, parallel runs and spare feeder
AC illustrative purchase360 × 1.05378 route-mCable type and earthing conductor

Put measured length, contingency and order rounding in separate columns. That makes later revisions visible instead of silently increasing every cable line.

AC-side equipment, transformer and grid interface

The example assumes four 200 kW AC inverters, so the inverter line reads four units, not “800 kW” as a purchase quantity. Each unit needs an exact model and input/output limits before release. The AC collection board, breakers, protection devices, meters, cable terminations and communication hardware are separate lines. An inverter may include some protective functions internally; the BOQ still needs to show what external switchgear the electrical design and grid interface require. Do not duplicate an included device, and do not omit one by assuming a catalogue feature is present.

Whether the plant needs a dedicated step-up transformer, HT panel, ring main unit, metering cubicle or evacuation line depends on its grid connection and ownership boundary. The phrase “1 MW plant” cannot determine the voltage or quantity of those assets. The interconnection offer and SLD must fix the point of connection. If the project exports at an HT bus, the BOQ may need a transformer, HT switchgear, protection relay, CT-PT metering and cables. If it connects behind an existing consumer supply, the scope may be different. A transformer capacity cannot be set equal to 800 kW without considering kVA, power factor, operating conditions, losses and the approved scheme. Treat that line as TBD by electrical design until those inputs are known.

The CEA construction standards register lists the 2022 regulations and 2025/2026 amendments. Site-specific electrical design and the applicable version should be checked by the responsible engineer. A BOQ need not quote every clause, but its specification column should identify the standard, drawing and data-sheet basis for critical equipment. “As per latest standard” is difficult to price because bidders may make different assumptions.

AC/grid itemExample quantityWhy it cannot be final yet
200 kW AC string inverter4 eachExact model and input/output compatibility open
AC collection board1 provisional assemblyFeeder count, protection, fault duty and metering pending SLD
Inverter-to-board feeders4 provisional circuitsCable construction and sizing pending route and load checks
Step-up transformerTBDGrid point, voltage and kVA design not supplied
HT switchgear/RMUTBDUtility scheme and ownership boundary not supplied
Export/generation meters and CT-PTTBDDISCOM/utility agreement and metering scheme not supplied
SCADA/monitoring and communicationsTBDContract and integration requirements not supplied

“TBD” is a valid design-stage quantity status. It should be resolved before a fixed-price procurement issue, not converted into zero.

Mounting structures, foundations and civil works

The module layout is the starting point for steel quantity, but it is not the steel quantity itself. For a simple arithmetic illustration, put 16 modules per table. Then 1,600 ÷ 16 = 100 tables. If a hypothetical preliminary table sketch shows four supports per table, it yields 400 support locations. These numbers do not establish the number, size or depth of piles. Row spacing, tilt, terrain, module dimensions, wind load, corrosion environment, geotechnical bearing capacity, uplift, drainage and access all affect structure and foundation design. A final BOQ should take steel by member size and length, hardware by connection, and foundations by an approved civil/structural design.

The NREL ground-mount component study lists geotechnical investigation, clearing, grading, compaction, trenches, vertical support foundations and horizontal supports as separate work categories. Use it as a reminder that a ground-mount plant is more than tables and modules. A site with uneven terrain may need grading and drainage; a flat site may still need access roads, perimeter protection or temporary construction facilities depending on contract. The land survey and civil design decide the quantity, not the 1 MW label. If there are 100 tables, it does not follow that there are 100 identical trenches or 400 identical foundations.

Make a drawing-linked quantity register. For each structure type, record table ID range, module arrangement, steel assembly, coating specification, fastener set, foundation type and drawing revision. For civil works, record trench cross-section and length, road width and area, concrete volume, excavation and backfill separately. A trench can include more than one cable, so cable route and excavation quantities should have different measurement rules. If the tender pays for excavation by cubic metre, a length-only “trench” row is incomplete until its section and site conditions are specified. If rock excavation is possible but not surveyed, flag it as a provisional quantity with an explicit adjustment mechanism.

Civil/structure lineExample statusCorrect quantity basis
Module mounting tables100 assumedApproved GA and table schedule
Supports/foundation locations400 hypotheticalApproved structural and geotechnical design
Steel members and railsOpenMember schedule, lengths, mass and coating
Fasteners and clampsOpenConnection detail and module count
Piles, pedestals or footingsOpenFoundation drawings and soil report
Trenches, ducts and backfillOpenRouted length, cross-section and material schedule
Access, fencing, drainageOpenCivil/site plan and contract boundary

Do not present the hypothetical support count as an engineering recommendation. It exists to show how a layout assumption propagates into a BOQ and why it must be replaced.

Earthing, protection, testing and small items

The lines that look minor individually can become significant when repeated across 100 tables and many cable routes. Earthing conductors, bonds, connectors, earth electrodes or grid materials, test links, surge protection, labels, cable glands, lugs, ferrules, trays, conduits, termination kits and spare hardware need their own measurement basis. Do not use “one earth pit per table” as a shortcut. The earthing design depends on site conditions and electrical fault behaviour, and must be engineered under the applicable requirements. The CEA safety standards register identifies relevant construction and operating safety rules; the project engineer must select the current applicable edition and local requirements.

Commissioning also has a measurable scope. The EPC may need insulation resistance testing, polarity and continuity checks, protection settings and functional tests, meter tests, performance tests, as-built drawings, O&M manuals, training and handover. Which items are contractor scope and how they are paid depends on the contract. An itemized BOQ can include labour/services rows as well as equipment. SECI’s 1 MW rooftop tender example asks for an itemized bill of material covering accessories and records as-built layout, SLD and structural drawings, showing why documentation should not disappear into “miscellaneous” when the buyer expects it.

The cost column should not precede the design basis. First define description, specification, unit, quantity, measurement rule, drawing reference, supply/installation owner and issue status. Then obtain rates for the actual equipment and scope. A rate without an exact model, service level or site condition is merely an assumption. There is no universal reliable ₹/MW BOQ because location, connection voltage, civil work and procurement boundary change so much.

For tender comparison, keep exclusions explicit: grid-connection fees, utility-owned works, taxes, permits, security fencing, land preparation, storage, spare modules and O&M are all possible boundaries. “Not in BOQ” must mean either assigned elsewhere or genuinely outside scope. If no one owns a necessary line, the project still needs it. A handover checklist that reconciles the BOQ to the SLD, general arrangement and contract scope can catch this before a bid is locked.

A release-ready BOQ workflow

  1. Freeze the definition of 1 MW. Record DC, AC and export limit separately.
  2. List the procurement boundary. Mark owner-supplied items, EPC supply, installation, testing, utility works and exclusions.
  3. Lock the equipment schedule. Use exact module and inverter models, then validate string design before counting accessories.
  4. Measure from coordinated drawings. Link every quantity to GA, SLD, cable route, civil and structure revisions.
  5. Keep units honest. Distinguish each, set, route-metre, conductor-metre, square metre, cubic metre, kilogram and lump sum.
  6. Show allowances separately. Document waste, contingency and order rounding. Avoid hidden percentage inflation.
  7. Resolve provisional lines. Transformer, HT panel, foundations and long cables cannot remain arbitrary in a fixed procurement issue.
  8. Cross-check the full file. Compare BOQ against drawings, specifications, tender, equipment data and responsibilities before release.

The existing method guide for calculating a solar BOQ covers the general workflow. This article adds a 1 MWp ground-mount example with traceable arithmetic and explicit open engineering quantities. Heaven Designs lists BOQs among its engineering deliverables. For a project-specific scope, send the approved layout, SLD, equipment list, civil survey and tender scope through the existing contact route to request a scoped response. Heaven Designs replies with scope, price and a delivery date; turnaround is agreed at scoping.

How many modules are in a 1 MW plant?

It depends on the definition of 1 MW and the selected module wattage. In this explicitly illustrative 1,000 kWp DC example, 1,000,000 Wp ÷ 625 Wp = 1,600 modules. A different module produces a different count. Verify model availability, tender conditions, layout and electrical compatibility before procurement.

How many strings and inverters are required?

The arithmetic example has 64 strings of 25 modules and four assumed 200 kW AC inverters. Neither number is a recommended topology. The series string must pass voltage and current checks with exact module and inverter data; the inverter count must fit grid, yield, availability and tender requirements.

Does the BOQ include a transformer and HT panel?

Only if the approved connection and procurement boundary assign those assets to the EPC. The plant capacity alone cannot answer that question. Obtain the interconnection offer and SLD, then specify voltage, ratings, protection, metering and ownership.

Can I use a standard cable length per MW?

Use it only as an early estimate clearly labelled as such. A release BOQ should measure the actual string, feeder and communication routes and specify cable construction, conductor count, sizing and allowances. The worked 4,850 conductor-metre DC figure above is tied to a fictional 35 m route and must not be reused as a site quantity.

Why are so many BOQ entries marked open?

The article has no site survey, soil report, approved grid scheme or exact equipment data. A professional BOQ makes those unknowns visible instead of making up a pile depth, transformer rating or trench length. Complete the design inputs, then replace each open item with a drawing-linked quantity and specification.

Sources checked 23 November 2026. The quantities and capacities in the worked example are assumptions for teaching arithmetic, not figures from the cited tenders or a Heaven Designs project.