For an assigned Component C feeder project, a solar site should be selected from the assigned feeder and substation outward. First obtain the implementing DISCOM’s feeder load and proposed interconnection point. Then test land access, distance and route to the substation, array area, terrain, drainage and grid connection works. A parcel that looks inexpensive or sunny can be a poor choice if the line route cannot be secured, the substation interface changes, or the feeder’s annual energy need does not support the proposed plant basis.
MNRE’s feeder-level solarisation guidelines describe a plant sized to cater to the agriculture feeder’s annual power requirement and connected at a distribution substation, potentially at 11 kV or a higher-voltage side depending on land and technical feasibility. The guidelines say a plant may serve one or more feeders. This is a scheme framework, not proof that a particular parcel, voltage, size or line route has been approved. The state implementing agency’s current tender and the DISCOM’s connection study control the actual project.
This article is an engineering desk and field checklist for developers and EPCs working from an assigned feeder or issued state RfS. It does not establish that a new award is available, or set eligibility, CFA, tariff, land compensation or construction schedule. Those are transaction and scheme questions that should be checked against current official orders. The Component C explainer covers the scheme context; here the job is to decide whether a specific feeder and parcel can support a plausible plant design.
Fix the feeder and the connection boundary first
The starting document is a written feeder or substation allocation, tender schedule or DISCOM communication. Record the feeder name and code, distribution substation, transformer or bus section, voltage, proposed metering point and any restriction on connection. A village name is not enough: two feeders serving nearby areas may have different load shapes, line conditions and available bays. Ask the DISCOM to identify the exact point at which the solar plant’s delivered energy will be accounted for.
MNRE’s original feeder-level guideline says the DISCOM or power department is the implementing agency, although a state may appoint another expert agency for tendering. It also says that separated agriculture feeders, or feeders with major agriculture load, can be considered. Do not turn those words into a universal eligibility test for a live bid. A current state RfS can define its own feeder list, capacity, performance and connection obligations. The technical team should work from that issued schedule and record its revision.
Request annual energy and, if available, hourly or time-block load data for the selected feeder. Annual units are needed to estimate a solar capacity, but the daily pattern also affects how much generation can be absorbed locally and how the project may operate. The 2020 MNRE guideline gives an illustrative feeder calculation using 10 lakh annual units, an approximately 600 kW plant and 19% CUF. It expressly allows different CUFs depending on the area’s solar resource. Do not copy that capacity to a new feeder without its actual load, meter boundary and modelled generation. The formula is a starting check, not a sanction.
Record whether the plant is intended to serve a single feeder or multiple feeders from one distribution substation. Identify switching and metering needed for the chosen arrangement. If the state tender permits a different voltage or additional non-agriculture energy use, document that separately. The concept SLD should mark proposed interfaces and unknown utility equipment, not portray a conceptual bay as already available.
| Feeder decision | Input to obtain | Engineering consequence |
|---|---|---|
| Assigned load | Annual units and seasonal/time-block profile | Candidate AC and DC capacity, yield comparison |
| Interconnection | Named substation, bay or feeder interface, voltage | Transformer, protection, metering and evacuation scope |
| Existing network | Feeder SLD, transformer ratings, line condition where released | Grid study questions and tie-in constraints |
| Ownership boundary | DISCOM and developer responsibilities in the RfS/PPA | Who designs, constructs and maintains line or bay |
| Approval path | Utility technical conditions and application stage | Drawing register and review programme |
These inputs may be commercially sensitive or incomplete. Mark their status. An EPC should not fill a missing feeder load with a guessed value and then label the output as a final plant size.
Evaluate distance as a route, not a circle on a map
“Near the substation” is an engineering objective, not one fixed national radius. MNRE’s feeder-level guidance says the DISCOM may identify land near the distribution substation and connect the plant through a sub-transmission line. It does not establish a universal five-kilometre rule. A 2025 Tamil Nadu government land EOI used a five-kilometre radius for its particular land-sourcing exercise. That is an example of a tender condition, not a rule to apply in other states.
A dated state example shows why the issued RfS matters. DHBVN Haryana RfS-06/PD&C/2024-25, published in 2025, identifies four sites with named substations and agriculture feeders, approximate spare land, and tentative plant capacities. It requires bidders who propose a higher cumulative capacity to base that choice on their own site survey, and its work scope includes the associated 33 kV or 11 kV line and remote monitoring. Those are conditions of that Haryana procurement, not a national distance or capacity rule. Confirm the current tender and amendments for the actual feeder before using any of its values.
Measure both straight-line distance and a plausible electrical route. The route may need road crossings, railway or canal permissions, private land access, changes in terrain, poles, towers or buried cable. Identify the proposed voltage and line technology only after checking the tender and utility conditions. A parcel three kilometres away in a straight line can be harder to connect than one farther away with a clear right-of-way and existing corridor. The design team should show the route length source and uncertainty on the concept plan.
Walk or survey the proposed route early enough to find hard blockers. Map boundaries, road and water crossings, settlements and utility assets. Ask who owns each segment and who will secure permissions. Do not assume that a land lease includes an evacuation easement. If line construction is a developer obligation, the bid or DPR needs an allowance based on a credible route, not a drawn arrow from parcel to substation.
The substation itself needs a desk check with the DISCOM. Is the proposed bay or connection point identified? Does the tender specify a new bay, augmentation or protection work? Who will provide drawings and settings? A developer can design a proposed interface, but the utility must confirm what it will accept. Keep that approval status explicit in the risk register.
Test land before drawing a full array
A parcel can appear large enough on a satellite image yet lose usable area to irregular boundaries, watercourses, access, slopes, drainage and excluded zones. Obtain cadastral and ownership documents from the responsible party and a ground survey for design. Map the parcel boundary and identify who has legal rights to use and reach it. Engineers can analyse physical layout but cannot certify title from a map.
Record terrain and water behaviour, not just area. Low-lying agricultural land may flood seasonally; cut and fill can alter drainage to neighbouring plots; soil can vary across the site. A basic geotechnical investigation and topographic survey may be needed before foundation design. If neither exists at bid stage, state the assumed foundation concept and the uncertainty. Do not present preliminary pile counts or steel quantities as final.
Check shading from trees, buildings, terrain and nearby lines at the time of survey. Mark what can be removed, what cannot, and what needs permission. A plant layout should preserve access for construction, cleaning, maintenance and emergency use under the project’s actual requirements. A densely packed array can increase nameplate capacity while making cable routes, access and shading worse. The land-fit study should compare options on delivered energy and constructability, not module count alone.
For each candidate parcel, prepare a short constraint map: boundary, exclusion zones, contours, proposed rows, inverter and transformer area, access roads, drainage path, line exit and substation direction. Attach source dates. If a drawing relies on a crop or terrain condition visible only in one season, flag that. A site visit can reveal a drainage channel or access conflict that an aerial image misses.
| Site test | Evidence needed | Hold condition |
|---|---|---|
| Boundary and access | Survey plus land/right-of-way documents | Site cannot be entered or line route cannot be secured |
| Usable area | Layout over surveyed exclusions | Proposed capacity depends on unverified land |
| Ground and drainage | Topography, water history, geotechnical data where needed | Foundation concept or flood risk unresolved |
| Shading | Site photographs and time-aware shade study | Material loss or removal permission unresolved |
| Grid route | Route survey and DISCOM interface note | Line length, crossing or bay obligation unknown |
The “hold condition” column tells a developer what to resolve before fixing the design basis. It is not an assertion that every state tender automatically rejects such a site.
Size the plant to feeder need and the selected connection
The annual feeder load is an energy number, while plant DC and AC capacities are power ratings. Convert between them only with a transparent energy model and meter boundary. Start with the feeder’s actual annual energy, then estimate plant generation using a stated weather source, equipment selection, layout, shading, losses and availability. Check the relevant tender’s rule for excess generation, feeder load, banking or other energy accounting. Do not assume all generated units have the same value or destination.
The simple CUF check is annual energy divided by rated capacity times 8,760 hours, expressed as a percentage. Its usefulness depends on which capacity rating and meter location the tender uses. The MNRE example of 600 kW for 10 lakh units at 19% CUF is explanatory. A real project may have different solar resource, weather year, shading, equipment or line loss. A plant sized from gross array energy but settled at a substation meter may overstate delivery if electrical losses are ignored.
Check grid equipment against the candidate capacity. A larger plant can require different inverter grouping, transformer, protection, metering and line scope. If multiple feeders share a plant, show how power and accounting are allocated under the approved arrangement. If the tender allows additional capacity for nearby non-agriculture loads, separate the agriculture feeder obligation from the extra generation in the model. The original MNRE guidance allows a state to consider enhanced plant capacity, but it limits certain scheme assistance to the agriculture-serving portion; current state and scheme documents must be checked before using that possibility commercially.
At concept stage, produce at least three linked outputs: a land-fit layout, a plant and connection SLD, and an energy-balance note. They should share the same DC/AC capacity, equipment basis and meter boundary. The layout should not show a capacity that the energy note cannot justify, and the SLD should not propose a voltage that the utility has not considered. Track each version in a drawing register.
Run a desk gate before spending on detailed design
The first gate asks whether the candidate is worth a full survey and DPR. Collect the tender or allocation, feeder load, substation details, parcel location and ownership status, a route map, satellite and field photographs, and any utility communication. Record each document’s date. In a short review meeting, ask: Is the feeder assigned? Is there a plausible connection point? Is the land usable and accessible? Can the line route be secured? Does the candidate plant size fit the annual feeder energy? Which facts are still only assumptions?
Classify each open item as designable with a stated assumption, requires external confirmation, or blocks the candidate. For example, a provisional module model may be designable within a specified size and electrical envelope. Unclear land access or an unconfirmed substation interface may block a confident bid. The decision depends on the RfS and the developer’s risk appetite; the engineer should make the technical consequence visible.
Use one decision sheet per parcel. It should show feeder ID, proposed site, distance by route, usable area, candidate capacity, energy estimate basis, major permissions, and next owner. Do not rank sites by a fabricated 100-point score. Compare the actual decision variables side by side, including uncertainty. A parcel with a lower theoretical yield can still be preferable if its grid route and land rights are clear.
After a candidate passes this gate, commission the right field studies and begin detailed engineering. Update the constraint map, SLD, yield model, BOQ and approval register together. If the DISCOM changes the connection point, re-evaluate the site instead of merely extending a cable line on the drawing. Engineering choice and transaction choice are linked here.
Send a feeder-specific brief for engineering review
Heaven Designs lists layouts, SLDs, BOQs, yield reports and structural calculations among its documented solar design deliverables. For an enquiry, send the feeder/substation reference, current state RfS, annual feeder energy, proposed parcel details, distance and route information, utility correspondence and required drawing stage through the contact form. The existing ground-mount design service covers broader plant engineering.
The scope reply can identify which site and connection questions are answerable from the supplied information and which require field or DISCOM confirmation, with price and delivery date for the defined work. No layout alone proves land rights, feeder suitability, scheme eligibility or utility approval. It should give the developer a controlled basis for the next decision.