A BOQ for a 100 kW rooftop solar plant should be a controlled list of equipment and work that the EPC can trace to its roof layout, electrical single-line diagram, cable routes, mounting details and connection scope. The 100 kW label by itself does not tell you the number of modules, length of cable, weight of structure or meter arrangement. Those quantities depend on the selected equipment and the site.
Working answer. Start the BOQ with the module and inverter schedule, then measure DC cable, AC equipment, mounting, earthing, access and protection from the current drawings. Put the source drawing, revision, unit and assumption beside each quantity. Separate measured values from provisional allowances. A rooftop BOQ needs special attention to roof attachment, cable risers, access routes and the customer’s existing electrical system.
This guide is for an Indian C&I EPC estimator preparing a tender, procurement schedule or execution revision. It provides a line-item framework and one transparent module-count example. It is not a purchasable bill for an unnamed 100 kW project. The responsible engineer must verify equipment ratings, the roof, electrical connection and applicable authority requirements before a bid or purchase order is issued.
First decide what “100 kW” means in the tender
A plant may be described by DC module capacity, AC inverter capacity, sanctioned grid-export capacity or a tender’s named capacity. These are different values. If a buyer says “100 kW rooftop solar,” ask whether that is 100 kWp DC, 100 kW AC, or a maximum at the connection point. Record the answer in the BOQ header and use the same basis in the layout, SLD and application. A mismatch can alter the number of modules, inverter choice, protection and metering scheme.
Here is a simple illustrative calculation, not a specification for a real project. Assume the design target is about 100 kWp DC and an approved module is rated at 550 Wp under its nameplate test conditions. Dividing 100,000 Wp by 550 Wp gives 181.82 modules. Because modules are indivisible, 182 modules yield a nameplate total of 100,100 Wp, or 100.1 kWp DC. The arithmetic is 182 × 550 Wp = 100,100 Wp. If the tender requires a strict upper bound of 100.0 kWp rather than an approximate target, 182 modules may exceed it; 181 modules would total 99.55 kWp. The tender wording decides which result is acceptable.
This example has no roof plan, shading survey or actual module data sheet. It does not prove that 182 modules fit the roof, that the string voltage is valid, or that any particular inverter accepts the resulting array. The mounting design, fire and maintenance access, setbacks and roof load may reduce the usable area. Equipment substitutions change the count. Treat the number as a demonstration of unit handling and rounding, not as a default quantity to paste into another EPC quote.
| Example input | Value | Unit | Where a real project gets it |
|---|---|---|---|
| Stated DC target | 100 | kWp | Tender or design brief |
| Illustrative module rating | 550 | Wp per module | Selected model’s current data sheet |
| Exact division | 181.82 | modules | 100,000 Wp ÷ 550 Wp |
| Rounded example quantity | 182 | modules | Design decision after roof and electrical checks |
| Resulting nameplate DC total | 100.1 | kWp | 182 × 550 Wp ÷ 1,000 |
Do not apply the same rounding logic blindly to inverter quantity. An inverter schedule needs the actual DC/AC design ratio, stringing limits, voltage and current envelope, mounting location and grid interface. A theoretical 100 kW AC configuration could use different inverter counts. The engineer should select and check the model, then the BOQ should record the chosen count and data-sheet revision.
Build the BOQ around drawings, not a generic price sheet
The first columns in a useful BOQ are item number, description, unit, quantity, source drawing or schedule, revision, and status. Rate and amount columns can be added for a priced tender, but they should not hide the measurement basis. A procurement team should be able to ask why the AC cable length changed and receive an answer tied to an inverter relocation or a route revision. A spreadsheet cell with no drawing reference cannot provide that answer.
Use a common revision register. The module layout controls panel count and array arrangement. The string plan controls DC circuit counts and connection points. The SLD identifies inverters, AC boards, disconnects, protection and the point of connection. Roof sections and mounting drawings control support members, rails, clamps, anchors and waterproofing interfaces. Cable routing drawings control path lengths. The BOQ should state which revision of each document was measured. A tender-stage concept quantity should be marked provisional where details are still open.
This is especially important for an existing factory or commercial roof. The solar work often ends at an existing LT panel or transformer that the EPC did not design. The estimator must name the boundary: does the contractor supply only the solar AC feeder, or also a new outgoing breaker, panel modification, meter cubicle, shutdown interface or test? Are access ladders, walkways and roof strengthening included? A clearly excluded item is easier to price and discuss than a silent gap discovered after award.
The SECI 100 kW rooftop tender for the NIWE campus, published in August 2026, is a useful public example of why the tender itself controls scope. That project includes dismantling existing work and hybrid capability, so its schedule should not be copied into a simple grid-connected C&I rooftop BOQ. It demonstrates the need to read the technical scope and amendments before reusing a quantity format.
DC field: modules, strings and route-dependent material
Begin the DC section with modules by exact model or approved technical specification. Record the rating unit and quantity basis. If the model is provisional, do not make a compliance claim about it. Add manufacturer-supplied connectors or field connectors only where the supply split calls for them. A connector included with a module lead should not be counted as if it were a separate loose item unless the design actually needs additional parts. Conversely, extension cables and termination accessories can disappear from a bid when the estimator treats the factory leads as sufficient for every roof geometry.
The stringing plan gives the number of strings and their destination. It also exposes whether different roof planes or orientations need separate inverter inputs. Do not derive a string count merely by dividing module count by a convenient number. The selected module and inverter data sheets, temperature range, maximum voltage, current limits and design standard govern the electrical decision. Once the engineer approves a string plan, the BOQ can count string cables, connectors, junctions, protection devices and labels with a traceable source.
For cable quantities, distinguish route length from purchased conductor length. A 30 m path on a roof is not necessarily 30 m of DC cable. Positive and negative conductors, multiple strings, risers, approach to equipment, termination allowance and the route to the AC point can change the total. A cable schedule should give the number of circuits, conductor arrangement, selected size and the drawing route. If the route is only conceptual, label its quantity as an estimate and identify the allowance method. Avoid a fixed “metres per kW” rule.
The Central Electricity Authority’s electrical safety regulations page addresses appropriately rated cabling, protection, isolation, routing and earthing. These requirements support the categories that a BOQ should not forget. They do not supply a universal cable size, number of surge devices or earthing-pit count for all 100 kW roofs. The design engineer selects those values from the project conditions and current applicable rules.
| DC line-item group | Unit usually measured | Source to inspect | Common omission to check |
|---|---|---|---|
| PV modules | number | Module layout and approved model | Wrong model or DC total |
| Field connectors and extensions | pair or number | String plan and module-lead lengths | Counting factory connectors twice or missing extensions |
| DC conductors | metres by size/type | Cable schedule and measured routes | Riser and termination length |
| Cable containment | metres or sets | Roof route and support details | Separate tray covers, brackets and fittings |
| DC protection/isolation | number or set | SLD and equipment schedule | Unclear supply boundary |
The table is a review aid. A real tender may use a different unit or combine lines according to its schedule. Make the BOQ match the document that will be priced and procured.
Inverters, AC equipment and the existing LT interface
The AC section starts with the approved inverter schedule. Include the model and quantity, the mounting or enclosure accessories that are genuinely separate, monitoring interfaces where in scope, and the AC connection equipment shown on the SLD. Then list the AC feeder by conductor type and size, the protection device, panel or combiner, and the connection work at the customer’s existing electrical installation. Do not assume that every 100 kW rooftop needs the same LT panel or transformer. The connection architecture depends on the customer supply and the utility’s requirements.
At a C&I site, the point of connection may sit inside an existing panel. The EPC needs evidence about spare ways, busbar rating, fault level, metering and shutdown arrangement. A sales-stage single-line diagram often lacks this information. Mark an existing-board modification as provisional until the responsible engineer and site team verify it. If the customer owns the modification under a separate contract, record that interface as an exclusion with a named dependency. The BOQ should make procurement ownership unambiguous.
Metering is another frequent boundary. Whether the project uses net metering, net billing, zero export or another arrangement depends on the customer and relevant regulatory or utility process. A BOQ should reflect the chosen design and identify meters, CT/PT, cubicles or communication items only when required by that scheme. The EPC should not buy a generic “solar meter kit” from an old quote before the connection application and metering specification are understood. Where a state rule is volatile, record the current order and effective date in the project file rather than in a copied price sheet.
Label AC cable quantities like DC quantities: route, circuits, number of conductors, size and allowance. The height of the building, inverter position, cable tray route and approach to the connection point can make a 100 kW rooftop materially different from another. A transparent quantity lets the estimator price the work and lets the engineer update it when the inverter location changes. An unexplained lump sum does neither.
Roof structure, waterproofing and access belong in the take-off
A rooftop BOQ is not a scaled-down ground-mount BOQ. The roof is an existing structure with its own geometry, condition and limits. A trapezoidal sheet roof, standing-seam roof and concrete terrace need different attachment concepts and different components. The mounting designer must check the roof and load path. The BOQ then follows the approved mounting details: rails or purlins, brackets, clamps, fasteners, roof interface and any specified corrosion treatment. Do not infer steel weight from the plant capacity alone.
The roof survey should identify obstructions, skylights, vents, gutters, equipment, fall hazards and available access. Module placement can change when a structural engineer rejects a span or the facilities team needs a maintenance route. That change affects module count, mounting members, cable route and sometimes inverter location. A mature BOQ process waits for the controlled layout and then records the design change, instead of pretending the first sales drawing is the final procurement document.
Waterproofing is a scope issue as well as a technical issue. Penetrating mounts may require specified sealant, flashing, testing and warranty coordination. A non-penetrating system may affect ballast and roof loading. The EPC should ask who designs and executes the roof interface and whether the building owner has material or method restrictions. Put separate BOQ lines where the purchasing or installation responsibility differs. “Mounting structure complete” may be too vague when the roof contractor must coordinate penetrations or repair existing sheets.
Access, safety and maintenance provisions also need an explicit decision. The CEA’s solar safety chapter discusses roof pathways and access, but the final layout must be checked against the current applicable rule and local fire, building and customer requirements. Do not copy a walkway width from a different jurisdiction into a tender without confirming its applicability. If the design requires a walkway, ladder, handrail, anchor point or service clearance, show its location and measurement basis. If another contractor supplies it, record the interface so the solar BOQ does not imply it is included.
| Rooftop decision | BOQ consequence | Evidence required |
|---|---|---|
| Sheet roof versus concrete roof | Different clamps, supports or anchorage | Roof survey and mounting detail |
| Structural capacity or span change | Different member sizes, layout or reinforcement | Engineer’s assessment and approved drawing |
| Roof penetration | Flashing, sealant, testing and responsibility | Detail and owner approval |
| Access route | Walkway, clearance or other works | Final layout and applicable rule |
| Inverter location | Mounting, AC/DC cable and tray lengths | Equipment location drawing |
The table maps decisions to potential line items. It does not claim that every 100 kW rooftop requires all five works.
Earthing, protection, testing and close-out lines
The electrical BOQ should include the earthing and bonding system shown in the approved drawings, not a generic fixed count of earth pits. Count conductors, strips, electrodes, connectors, test links and other components according to the design and the project’s governing standards. The CEA solar safety requirements are a starting regulatory source for Indian projects; the earthing design must be site-specific. Soil, existing earth network, structure and connection details matter. A line labelled merely “earthing complete” can be difficult to price and inspect unless the associated drawing and scope are clear.
Protection and isolation items need the same discipline. The SLD should identify the relevant switchgear, protective devices, surge protection and isolation points; the equipment schedule should identify ratings and models when selected. The BOQ can then count the specified hardware and identify whether it is supplied inside a purchased inverter or as a separate item. Double counting an integrated component wastes money; omitting a required external component leaves the installer short. The engineer should verify the final arrangement against the equipment data and applicable rules.
Testing and commissioning can appear as work lines even when they have little material quantity. Who performs insulation resistance testing, continuity and earthing checks, inverter setup, protection verification, meter coordination and handover? What records are required by the customer or utility? These are project-scope questions. A BOQ that lists only equipment can understate the work needed to deliver a usable plant. The tender may require separate schedules for materials and services; use its format rather than forcing all costs into material rows.
Add documentation and close-out where the contract asks for it: as-built SLD, equipment manuals, test records, warranties supplied by manufacturers, and an operations handover. Do not promise a particular warranty period or approval result from a BOQ line. The line should describe the document and responsible party. If the project requires an engineer’s certificate or authority submission, name the exact scope after verifying the jurisdiction and agreement.
Reconcile the BOQ before pricing or procurement
Before commercial rates are entered, perform a cross-document review. Count modules on the layout and compare that count to the schedule and DC capacity calculation. Compare inverter quantities and ratings to the SLD. Follow every DC and AC feeder from its source to destination. Check the cable schedule against the route drawings. Compare mounting members and attachment counts against the latest structural details. Confirm that access and safety items shown on the roof plan appear in the work scope. Finally, mark every provisional quantity and excluded interface in a register that the estimator can see.
After the bid, do the review again against the issued-for-construction drawings. The difference between tender and execution quantities should be recorded line by line with the reason and drawing revision. A module substitution may change count and rail spacing. A moved inverter may change DC and AC cable. A changed roof-attachment detail may alter clamps and waterproofing. Changing one row without following those downstream effects produces a spreadsheet that no longer describes the plant.
The site’s solar BOQ calculation guide explains a broader method for measuring groups. This article focuses on what a 100 kW C&I rooftop makes different: the existing roof, the LT interface, maintenance access, and the risk of measuring from a sales layout. Heaven Designs lists BOQs among its engineering deliverables. Send your current layout, SLD, roof information and tender format through the contact page to discuss a project-specific scope, price and delivery date.
Sources checked 23 November 2026: CEA Measures Relating to Safety and Electric Supply regulations including the listed solar-installation requirements; SECI’s 2026 100 kW NIWE rooftop tender. The calculations above are explicitly illustrative. Check the current tender, utility instructions, building conditions, equipment data sheets and adopted standards for a live project.