An HT-connected rooftop solar plant needs a single line diagram that explains the complete electrical interface, not just the PV array. The drawing should let the EPC, facility electrical team, utility and safety reviewer trace the path from strings and inverters through AC collection, transformer if used, HT switchgear, metering, protection and the agreed connection point. It should distinguish existing equipment from proposed equipment and identify who owns each boundary.
Quick answer. For an 11 kV rooftop solar connection, draw the DC source, inverters, LT collection, transformer arrangement if present, HT switching and protection, CT/PT metering where specified, and the utility or consumer tie-in point. Label the selected equipment and ratings, show the relevant relay functions and control interfaces, and coordinate the SLD with the earthing, layout, protection study and utility conditions. The exact meter position and protection settings are project decisions. A generic 11 kV template cannot settle them.
Rules checked: 23 November 2026. The Central Electricity Authority publishes the current distributed-generation connectivity regulations, electrical safety regulations, and metering regulations with later amendments. The relevant state regulator and distribution licensee supply the project-specific connection and metering conditions. This guide is a drawing review aid, not a design approval or relay-setting schedule.
First decide what “HT-connected” means at this site
An 11 kV consumer connection does not automatically tell you where the solar plant connects. The facility may receive supply at 11 kV and transform it to LT for most loads. Its rooftop PV inverters may connect to a verified LT bus, to a dedicated step-up transformer and HT bay, or through another engineered arrangement. Each case changes the SLD. The phrase “11 kV rooftop” describes the consumer’s supply or a proposed interface, but it does not by itself specify the solar tie-in voltage.
Begin with the existing electrical system. Ask for the latest approved overall SLD, transformer and switchgear schedule, metering arrangement, sanctioned or contract demand details, and the facility’s present operating modes. Walk the actual point of connection with the facility electrician or responsible engineer if the drawing is old. A CAD file can preserve a panel label after that panel has been replaced. The project SLD needs a verified existing baseline, with assumptions marked until confirmed.
The next question is who owns the equipment around the point of interconnection. An HT meter, CT/PT unit, consumer VCB, transformer, LT main board and solar ACDB may sit on different sides of a utility or customer responsibility boundary. The drawing should show those boundaries and identify any licensee-owned equipment. Do not infer a meter or protection position from another factory’s SLD. The licensee’s technical feasibility or connection conditions should settle the interface.
For a Gujarat project, the GERC Grid Interactive Distributed Renewable Energy Sources Regulations, 2026 require the distribution licensee or other competent network entity to specify the interface, interconnection and metering points and the protection and communication requirements for the applicable arrangement. The notification replaced the older 2016 rooftop net-metering framework. For projects in other states, use that state’s current regulation and utility procedure instead. In every case, the SLD should be drawn against the issued conditions, not a remembered net-metering rule.
| Site question | Why it changes the SLD | Evidence to obtain |
|---|---|---|
| Is PV tied to LT or HT? | Determines whether a solar step-up transformer and separate HT switchgear appear | Approved connection concept and existing SLD |
| Is the transformer existing or new? | Changes ownership, protection and equipment schedule | Transformer nameplate, drawings and utility conditions |
| Which meter records import and export? | Changes meter placement and CT/PT representation | Current metering approval or licensee instruction |
| Is DG or storage present? | Adds operating modes and anti-backfeed controls | DG or BESS SLD and control narrative |
| What is the approved boundary? | Defines the handoff between consumer and licensee systems | Connection agreement or technical feasibility letter |
This first-stage classification is the main reason an HT rooftop SLD needs its own guide. A basic solar diagram can teach the reader what a breaker or inverter symbol means. An HT design must show how those pieces fit into a live industrial electrical system and an approved interface. If the connection basis is uncertain, the correct deliverable is a marked-up design concept with open decisions, not a submission-ready drawing.
The equipment path an 11 kV SLD should make legible
Trace the plant from source to interface. On the DC side, the SLD should identify PV strings or array groups, inverter inputs, DC isolation and combiner equipment where used. The inverter block should show the exact model or approved equipment basis, number of units, AC voltage and rating. On the LT AC side, identify each collection board, feeder, protective device and destination. If the solar plant steps up to HT, show the transformer with its relevant electrical particulars and the path onward to the HT switchgear and metering.
At the 11 kV interface, show the actual switching arrangement. A vacuum circuit breaker, isolator, earth switch or other apparatus belongs on the sheet only when the engineered scheme uses it. Label the equipment and drawing references consistently with the switchgear schedule. The SLD should distinguish existing bays from proposed bays and indicate where protection and metering CTs or VTs are installed. Where the project calls for a new bay or modification to an existing panel, make that scope clear rather than drawing a single unexplained line into the switchboard.
The drawing should also show the status of auxiliary interfaces that matter to protection and operation. Examples include anti-islanding, trip paths, zero-export controller sensing, DG interlocks, remote trip or communication arrangements. Their detailed wiring may live on a separate schematic or control drawing, but the overall SLD should make the functional relationship clear enough to identify missing interfaces. A box called “controller” without its measurement point or trip destination gives a reviewer little information.
| SLD block | Minimum project-specific information | Check against |
|---|---|---|
| PV and inverter | String grouping, inverter number and selected AC output | String plan and datasheets |
| LT collection | Board tags, feeder destinations and protective-device identification | AC layout, panel schedule and cable design |
| Transformer, if used | Source and destination voltages, capacity, winding and earthing basis | Transformer schedule and protection study |
| HT switchgear | Existing and proposed bays, switching devices and equipment tags | Approved existing SLD and switchgear records |
| CT/PT or VT | Location, purpose and identified ratios where approved | Metering conditions and protection design |
| Relays and controls | Functions, trip boundaries and relevant interlocks | Protection study and control narrative |
| Grid or consumer point | Exact physical/electrical tie-in and ownership boundary | Utility technical feasibility and connection letter |
The table is a document-control checklist, not a ready-made equipment schedule. It does not prescribe a VCB size, CT ratio, relay setting, transformer vector group or cable size. Those values depend on fault levels, load and generation, protection coordination, equipment selection and the licensee’s requirements. The CEA connectivity standards for distributed generation and the relevant utility conditions provide the regulatory basis; the project engineer must perform the design.
Metering and CT/PT: show the approved arrangement
HT metering is a frequent source of ambiguity because a plant can have more than one meter with different purposes. The existing consumer import meter may not be the only meter needed. A generation meter, bidirectional meter, check meter or other metering equipment may be specified for the selected arrangement. CT/PT units may serve revenue metering, protection, or both, but their functions and locations should be distinguishable on the SLD. Do not put a generic CT symbol on the line and leave the reader to infer its purpose.
The national baseline includes the CEA Installation and Operation of Meters Regulations, 2006 and amendments. Those regulations have 2026 amendments, so a copied older meter detail should be checked against the current consolidated rule. State and utility procedures determine the particular meter scheme at the connection. In the Gujarat 2026 DRES rules, the model agreement says the distribution licensee or competent entity specifies the metering point and arrangement. It also distinguishes metering by net, gross and other arrangements. This is why the EPC should write the selected settlement route at the top of the drawing brief.
For net metering or net billing, the relevant interface meter arrangement needs to represent imports and exports according to the approved terms. For gross metering, generation and consumption are accounted separately under the Gujarat model terms. The SLD should therefore label meter locations and directions without implying that all projects have the same settlement. A drawing cannot choose a tariff or entitlement; it must reflect the approved contract and metering design.
Practical review starts with three questions. First, is the meter on the side of the transformer or connection boundary that the licensee specified? Second, are CT/PT ratios, accuracy requirements, test certificates and sealing provisions shown or referenced where the utility requires them? Third, do the SLD, meter schedule and cable layout describe the same system? A well-labeled SLD is still inconsistent if the meter schedule lists a different unit or CT ratio.
Avoid specifying a CT/PT ratio from the PV capacity alone. Meter selection depends on the service configuration, expected current, accuracy class and licensee conditions. Where a utility design review is pending, mark the metering arrangement subject to utility confirmation in the controlled drawing rather than making an unqualified submission claim. This is not a cosmetic note. It tells procurement and construction teams that the metering equipment should not be ordered solely from the draft sheet.
Protection functions and the trip boundary
An 11 kV solar interface has to be safe during faults, grid loss, maintenance and abnormal operating conditions. The SLD should show the protective-device locations and the relay functions applicable to the chosen design. It should indicate which circuit breaker each protection element trips and how isolation works across the customer and utility boundary. The detailed settings are the output of a protection design and coordination study, not a number to borrow from a generic website.
The CEA distributed generation connectivity regulations and CEA safety regulations, including listed amendments, form the national baseline. The utility can add interface requirements through its technical feasibility letter, connection agreement or approved procedure. Gujarat’s 2026 DRES model terms require suitable isolation and anti-islanding and place responsibility for technical and protection compliance before synchronisation. The EPC should point to those actual source documents in its drawing review record.
Depending on the system, the design may call for overcurrent, earth fault, under/over-voltage, under/over-frequency, reverse power, anti-islanding, transformer differential or other functions. This list is not a recommendation that every 11 kV rooftop plant needs every function. The protection study and authority conditions decide what applies. The SLD should identify the selected functions with standard, legible labels and show their equipment associations. A relay symbol placed near a VCB but with no clear CT source, trip path or setting reference is incomplete for engineering review.
Check the trip boundary carefully. If the grid supply fails, which breaker opens? What happens at the inverter? What does the facility’s DG system do? If a zero-export controller is present, where does it measure power and which inverters does it command? The overall SLD cannot draw every wire, but it should point to the control or protection schematic that answers these questions. Separate normal operating, grid-loss and maintenance conditions in a short control narrative. That narrative can prevent two contractors from assuming that the other supplied an interlock.
The final relay settings, tests and commissioning records should be reconciled with the approved drawing. The Gujarat 2026 regulation says the system must not synchronise until protection, metering, safety and other technical requirements have been met and the competent authority has granted the necessary approval. An SLD issue alone is not that approval.
Transformer and earthing details that change the diagram
Some rooftop projects inject at an LT bus behind an existing 11 kV consumer transformer. Others use a dedicated transformer to connect PV generation at HT. The SLD must depict the actual arrangement, including which transformer is existing, which is proposed and whether the PV connection is on the LV or HV side. The vector group, earthing, neutral treatment and protection devices are design information. If those values are not selected or verified, mark them as open and do not present the sheet as final.
The transformer block also affects the protection boundary. A new solar transformer may require a dedicated breaker and associated relay scheme. An existing consumer transformer may already have protection that must be checked for the changed power flow. Reverse power through existing equipment, transformer loading, busbar capacity and fault contribution all deserve engineering review. None can be cleared simply by showing a transformer symbol. The SLD should cross-reference the protection study, transformer datasheet and existing-system verification.
Earthing is a companion design, not a single earth symbol sprinkled across the SLD. Show the relevant earth and neutral relationships on the one-line and refer to the project earthing layout and calculations where required. The Gujarat Chief Electrical Inspector’s older certification checklist lists an overall SLD and a separate earthing layout for HV/EHV installations. It is a dated example, not a current solar-specific filing rule. Confirm the actual drawing list with the inspectorate for the project.
Before final issue, compare the transformer and earthing representation across the SLD, equipment layout, earthing drawing and BOQ. If one document includes a neutral earthing resistor, earth transformer or separate pit that the others omit, the inconsistency needs resolution. A reviewer should be able to trace the selected transformer and protection arrangement from source document to drawing and procurement schedule without guessing.
A pre-submission check for the EPC reviewer
The most efficient SLD review follows the power path and then checks the documents that support it. Use the steps below as a review sequence, not as a replacement for the competent engineer’s technical calculations or the authority’s current checklist. Record the date and version of each source used. A design can be correct under one utility condition and wrong after the tie-in point changes.
- Confirm the existing baseline. Compare the latest approved site SLD with the verified switchgear, transformer and metering equipment. Mark uncertain assets as survey holds.
- Confirm the solar path. Count inverters and strings against the layout and selected datasheets. Trace DC and AC circuits to the proposed bus or transformer.
- Confirm the HT interface. Identify the 11 kV bay, VCB or other selected switchgear, isolation and ownership boundary. Check the tie-in against the utility letter.
- Confirm metering. Compare all meter and CT/PT locations and details with the agreed settlement arrangement and licensee requirements.
- Confirm protection. Ensure each selected function has a defined measurement point, device association and trip boundary. Cross-reference the protection study and control drawings.
- Confirm companion documents. Reconcile the SLD with the equipment layout, earthing drawing, cable schedule, transformer schedule, BOQ and document register.
- Confirm issue control. Check drawing purpose, revision, project identity, notes and engineering reviewer. Record unresolved points before submission.
The common errors are surprisingly concrete: the PV inverters are tied to a board with no verified rating; a meter is drawn on the wrong side of the connection point; an existing transformer is presented as a new procurement item; the protection relay is named but has no trip destination; or the SLD and BOQ count different inverters. Each error can move into procurement or construction if the sheet is treated as self-validating. The checker should sign the controlled revision only after the underlying documents agree.
If the reviewer returns a comment, identify every affected document. A moved connection point can change the SLD, cable route, protection basis, metering detail and BOQ. A changed inverter model can alter currents and device selection. Close the comment with a revision record, not just a new PDF attachment bearing the same filename. This is how the EPC can tell the site team what was actually approved for construction.
The guide to reading a solar SLD explains the general symbols and power path. For a project-specific HT drawing, bring the existing SLD, utility conditions, equipment list and intended connection point to a qualified electrical design team. The existing electrical and CEIG drawings service is the relevant live route for a scoped drawing set.
What to send for a project-specific drawing review
The best brief is a compact document pack with a clear decision to be made. Include the facility’s current SLD, utility bill or service details, sanctioned or contract demand, transformer and HT panel particulars, proposed PV capacity, selected module and inverter datasheets, rooftop layout and string plan, and the exact proposed connection point. Add the distribution licensee’s technical feasibility or connection letter, the current metering instructions and any CEI or inspectorate comments. If a DG set or battery exists, include its drawing and operating narrative.
State whether you need a concept SLD, authority submission, construction issue or as-built correction. Ask the drawing partner to identify the inputs it will verify, the calculations and protection studies included, the drawing formats supplied, the expected review steps, and what happens when equipment or utility requirements change. This keeps a request for one sheet from silently expanding into an unpriced electrical redesign.
For an electrical drawing package, use Heaven Designs’ electrical and CEIG drawing service and request a project quote through its current form. Share the existing SLD, proposed tie-in, applicable utility conditions and the authority’s requested file list so the drawing scope can be defined. Approval and synchronisation remain decisions for the competent authorities and responsible engineers.
Does every HT consumer rooftop plant connect at 11 kV?
No. A consumer may receive 11 kV supply while its PV inverters connect at LT behind a transformer. The approved connection point and electrical scheme determine what appears on the solar SLD. Confirm it before drafting the final sheet.
Must the SLD show CT and PT ratios?
Show the selected metering and protection CT/PT arrangement with the details required by the utility and engineering design. Do not select ratios from plant capacity alone. If approval is pending, label the arrangement provisional and track it as a hold point.
Can one SLD replace an earthing or protection drawing?
No. The SLD identifies the major electrical relationships. The earthing arrangement, detailed control circuits and protection settings may require separate drawings and studies. The project checklist determines the complete file.
Can the rooftop plant be synchronised once the SLD is approved?
No. The drawing is one part of the approval path. The Gujarat 2026 model terms require compliance with technical, protection, metering and safety conditions and the competent authority’s commissioning or synchronisation approval before interconnection.