A solar shadow analysis report should let an EPC answer three questions: what creates shade, when and where it affects the proposed array, and how much of the modeled energy result depends on the shading assumptions. A single colored screenshot does not answer all three. A useful report includes the site evidence and geometry behind the model, a clear distinction between far-horizon and near-object shade, the selected electrical-shading method, quantified results with units and a design decision. It should also say what was not measured or modeled.

Request the report alongside the current layout and simulation file or model record. Check the site location, model date, module orientation, obstacle dimensions, roof or ground geometry, weather source, scene version and string arrangement. The study should connect the shading result to a layout choice such as row spacing, module movement, equipment relocation or a documented residual loss. If it gives a percentage without identifying its denominator and simulation boundary, ask for clarification before using it in a yield guarantee or investment case.

Methods checked: 23 November 2026. PVsyst’s shading documentation separates far shading from a horizon and near shading from nearby objects requiring a 3D scene. Its near-shading procedure explains that physical irradiance shade and electrical effects from module strings are different model treatments. A report should identify which treatment it used. These are software-method references, not a claim that every Heaven Designs study uses PVsyst or that one tool can verify the site by itself.

Show the site and model basis first

The report should start with project address or coordinates, time zone, site altitude if material, array orientation, roof or land plan, module and inverter selections, and the date of the source survey. A roof study should say whether geometry came from measured CAD, a drone survey, site photos, satellite imagery or assumptions. A ground-mount study needs terrain and adjacent obstacle information at a level appropriate to its decision. Each source has limitations. A photograph can reveal a tree but not prove its height; a satellite image can miss a new rooftop unit.

Provide a plan view that shows the modeled array and each relevant obstruction. Number or name obstacles so a reader can connect them to photos, dimensions and the 3D scene. Record parapet height, rooftop plant, nearby buildings, trees, poles and any future structure whose impact is being tested. If a tree crown or adjacent construction has uncertain dimensions, state the assumption and show its influence. The model is only as reliable as the geometry it represents.

The report should also state the array issue level. A bid layout may change after structural or fire review; its shadow result cannot automatically be reused for the final module positions. Put a drawing revision on the report and document the model scene version. An EPC can then tell whether the energy estimate was run on the same layout being priced. A shadow study on an obsolete roof plan can look precise while answering the wrong project question.

Report elementWhat the buyer should seeWhy it matters
Site and source recordLocation, survey date, dimensions, photosEstablishes model evidence
Array geometryModule rows, tilt, azimuth, height and layout revisionConnects shade to proposed design
Obstacle registerPosition, height, shape and confidenceExposes assumptions
Horizon and near-scene methodSeparate treatment and sourcePrevents one loss being confused with another
Electrical-shading basisString or module partition and methodShows whether mismatch was modeled
ResultsTime pattern, affected area and annual energy effectSupports a design choice
Sensitivity and exclusionsUncertain objects and future changesShows limits of conclusion

The table is a buyer’s review tool. It is not a prescribed PVsyst report format. The related how-to shadow analysis guide explains the modeling workflow; this article explains what an EPC should demand from a delivered report.

Distinguish horizon and near shading

A far horizon is represented as an angular boundary around the site. At a given sun position, it can block direct sunlight across the PV field more generally. Near objects cast local shadows with geometry that changes across modules and time. PVsyst describes these as different calculations. A report that shows one combined “shade percent” without explaining which sources created it is hard to review. Ask for the horizon source and the near-scene obstacle list separately.

Near-shading results depend on 3D geometry. Module rows can shade one another. Parapets and rooftop equipment can cast narrow shadows. Trees have uncertain seasonal shape. A model needs correct coordinates and heights for those objects, plus the array geometry. The PVsyst near-shading procedure explains why reconstructing the field and its surroundings is essential and why the resulting shading factor varies with sun position. A generic stock 3D view is not evidence that the real roof was measured.

State whether the analysis includes surrounding land use that might change. A new building next door, seasonal vegetation or temporary construction crane can affect future shade. The study should not promise that no future shade will occur. If an adjacent building is proposed but not built, show it as a separate scenario. A base case and a proposed-development case help the owner see the difference without merging the two into one unexplained yield figure.

Explain physical shade and electrical loss separately

The shaded area of an array is not equal to the electrical energy lost. A narrow shadow across cells can have an effect influenced by module wiring, bypass diodes, string arrangement and the software’s mismatch model. PVsyst’s near-shading dialog documentation distinguishes a linear irradiance treatment from an approach informed by module-string partitions. The chosen method and its limits should appear in the report. Do not treat a “string effect” screenshot as a measured field result.

Ask whether the model uses the actual stringing plan. At preliminary design stage, stringing may be provisional. A report can still compare layout alternatives, but it should label the electrical shading estimate accordingly. If final equipment changes, rerun the relevant model. A higher module count with a different string map may alter the electrical effect even if the roof geometry stays similar. The report should identify the stringing file or drawing revision it used.

PVsyst’s shading-factor-table documentation describes shading factors by sun position and notes method choices for fast tabulation versus more direct calculation. The EPC does not need every internal software variable printed, but it needs enough method detail to understand what was simulated. The report should distinguish annual irradiation loss, electrical mismatch loss and total energy effect. Those quantities have different denominators and cannot simply be added without respecting the model’s sequence.

Present results in a way the design team can use

Show a site/array figure with a legend, a sun-path or time view where it clarifies the impact, and a result table. For each relevant array zone, identify the shade source, affected period and modeled loss metric. Annual results should state the time basis and whether they reflect irradiance at the plane of array or energy at the inverter or delivery point. A percentage without units is incomplete. If the report includes monthly values, make them readable and note the weather data used.

Connect the result to a design decision. If one corner suffers morning shade from a parapet, compare leaving the modules there, moving them or omitting them, using the same module and weather assumptions for each option. If inter-row shade drives loss, compare row spacing with land use and cable consequences. A lower shade loss can require fewer modules or longer structures; the best design is not necessarily the one with the smallest shading percentage. Show the trade-off clearly.

Do not use arbitrary red-green score bands without criteria. The acceptable shade impact depends on contract terms, land or roof constraints, equipment cost, tariff or self-consumption value and the owner’s goals. A report can calculate differences; the EPC and owner decide whether the trade-off is worth making. If an energy yield study uses the shadow result for finance, record which report version and model case entered the finance model.

A worked review scenario without invented yield numbers

Consider an illustrative factory roof with a tall parapet along one edge and a row of mechanical units. The initial PV layout fills the entire clear roof. A site survey records parapet and unit heights. The analyst creates a 3D scene and runs two layout cases: modules against the parapet and modules moved away, with the same weather file and equipment model. The report includes a plan view, obstacle register, model screenshots, monthly shade pattern and annual energy comparison. It also records how many modules each case contains.

The EPC can then compare the added production from keeping edge modules against their shade loss and the roof access implications. If the fire authority requires a wider pathway, that may remove some modules independently of shade. The layout, string plan, yield report and BOQ should all use the selected case. This scenario has no fabricated production percentage or payback, because actual roof dimensions, weather and module behavior are absent. Its purpose is to show the report’s decision chain.

If the mechanical units are due for replacement, the analyst should flag that future height or location changes can invalidate the result. The owner can either freeze the equipment geometry or request a sensitivity case. A report that states this limit is more useful than one that gives an unexplained decimal-place loss.

Inspect the report for common gaps

First, check whether the model scene includes the whole relevant environment. A report may beautifully render the PV rows but omit a nearby water tank or future adjacent building. Compare the scene with current site photographs and the latest roof or plot plan. Second, check scale: are obstacle heights and array elevations documented? Third, check time: was the report run on an annual weather series or a single date? A winter-solstice screenshot can show a worst-looking shadow while saying little about annual energy without simulation.

Fourth, check loss labels. Does “near shading” mean beam-irradiance reduction or final electrical loss? Is the horizon loss counted separately? Is a string-effect method enabled? Fifth, check model consistency: is the module count the same as the current layout and BOQ? Sixth, check caveats: are vegetation, future structures, survey uncertainty and final stringing acknowledged? These checks require no single universal pass/fail threshold. They require a report that reveals how its number was made.

If the study relies on software that exports only a PDF, request screenshots or files sufficient to audit the scene and inputs. If a native model is part of the commercial scope, name the software version and file dependencies. A PDF can be enough to communicate a decision, but the EPC should not assume it can later edit a proprietary scene unless that file was contracted and delivered. Save the report alongside the drawing revision it supports.

Stage the study appropriately

At feasibility stage, satellite geometry and assumed heights may be acceptable for screening if labeled. At bid stage, more site evidence may be needed to price capacity and generation risk. At detailed design, surveyed dimensions, final equipment, roof access and stringing should feed the model. After installation, major changes to obstacles or modules can justify an updated as-built study if the owner needs it. The report should state its issue purpose so readers do not use an early estimate as a final guarantee.

The 3D solar pre-design service is a route for an early layout and shading enquiry. Ask for the exact scope: site survey assumptions, 3D scene, alternative cases, numerical result table, native model if needed and review of revisions. The design team can model and explain shading; site conditions and equipment choices still need verification by the responsible EPC.

Can a screenshot alone prove shade loss? No. It needs the site geometry, time and weather basis, model method and quantitative result.

Is near shading the same as horizon loss? No. PVsyst treats distant horizon and nearby-object geometry separately.

Does one shading percentage tell the owner which layout is best? No. Compare energy, module count, access, structural and commercial consequences for the same assumptions.

When should a report be rerun? When material geometry, obstacle, module, stringing or connection assumptions change enough to affect the conclusion.